PJM Interconnection, large load and co-located load tariff framework (FERC)
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusPending Last reviewed 2026-11-22
Applies atNot a retail tariff -- defines PJM's own 'Large Load' and 'Large Computational Load' categories and co-located-load service rules for its footprint
What the filing saysRead directly from FERC eLibrary's own filing index (filed tariff/testimony text itself not downloaded or read). Three related PJM FERC dockets: (1) ER26-3515-002 -- PJM's compliance filing implementing a 'Large Load Definition and Large Load Registry,' filed Nov 9, 2026, effective Oct 12, 2026 (already in effect by the time this compliance filing was made; the underlying rule that it complies with was not separately identified or read). (2) ER27-522-000 -- PJM's Nov 16, 2026 tariff filing under FPA section 35.13(a)(2)(iii), 'Operational Requirements for Large Computational Load and Annual Reporting,' proposed effective Jan 16, 2027; not yet acted on by FERC. (3) ER27-520-000 -- PECO Energy, filing on behalf of the PJM Transmission Owners, 'PJM TOs Tariff Revisions for Service to Co-Located Loads and Large Loads,' filed Nov 16, 2026, proposed effective March 16, 2027; not yet acted on. None of these three filings' own numeric terms (thresholds, reporting detail, co-location rules) were read this round. Re-checked Nov 18, 2026 (ER26-3515-002 reappeared in the fercElectric feed; checked the Federal Register's own document index for either docket by number, not the eLibrary filing text): no Federal Register notice of a FERC order has issued for ER26-3515-002 since the Nov 16, 2026 combined notice of filings already logged; still no order. UPDATE 2026-11-18: this run's regulator-filing-watch lead flagged a FOURTH PJM docket, ER27-531-000 ('Proposed Tariff Revisions for Large Loads and Compliance with EL26-67,' filed Nov 16, 2026, proposed effective March 16, 2027) -- FERC eLibrary's own Advanced Search API returned a server error for every request tried this session, and the filelist page is a client-rendered app this session's tools could not execute, so its own filed text was not read. Reported (Utility Dive, read directly, Nov 17, 2026), this appears to be PJM's own compliance response to FERC's EL26-67 show-cause order (separate from ER27-522 above): its centerpiece is a 'Fast Energization Process' that would study a large load's and a generator's interconnection requests together in a single, roughly one-year process (about twice as fast as PJM's current process), covering 'insufficiently fast interconnection processes for load and generation, parallel and duplicative study processes, speculative requests, limited visibility into the drivers of transmission upgrades, and an ongoing resource adequacy shortfall'; the overall proposal also addresses co-location/behind-the-meter generation rules, and PJM separately filed a requirement that large computational loads be able to ride through grid disturbances (this last point is consistent with ER27-522's 'Operational Requirements for Large Computational Load' above). PJM's transmission owners are also reported to have filed their own tariff covering rates, cost allocation, cost recovery, financial protections, revenue-crediting and transparency for service to co-located and large loads -- consistent with ER27-520 (PECO, on behalf of the PJM TOs) above. Re-checked Nov 19, 2026: ER26-3515-002 reappeared in the fercElectric feed again; the Federal Register's own document index shows no new notice or order since the Nov 16, 2026 combined notice already logged. Separately, PJM's own 'Critical Issue Fast Path: large load additions' watched page (pjm.com/committees-and-groups/cifp-lla) flagged a changed line this run, but the only differences were generic site-navigation menu labels ('About PJM,' 'Membership & Services,' etc.) -- a page-chrome re-render, not new content; no edit warranted. Re-checked Nov 20, 2026: the docket-watch queue flagged the same pjm.com/committees-and-groups/cifp-lla page again; re-fetched directly and confirmed the only changed lines are the site's own main-navigation menu text ('What We Do Advanced Technologies', 'Membership & Services...', 'Associate Enrollment'), not page content -- the Meeting Materials list is unchanged. Same navigation-chrome false positive as before, no edit.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
FERC eLibrary's own Advanced Search index (elibrary.ferc.gov/eLibrarywebapi/api/Search/AdvancedSearch), queried directly 2026-11-17 for accession numbers 20261109-5217 (ER26-3515-002), 20261116-5309 (ER27-522) and 20261116-5300 (ER27-520); the filed PDFs themselves were not downloaded or read. Federal Register document index (federalregister.gov/api/v1/documents.json), queried directly 2026-11-18 and 2026-11-19 for "ER26-3515": no order found since the Nov 16 combined notice. Utility Dive, 'Grid operators file closely watched large load interconnection reforms at FERC,' Ethan Howland, Nov. 17, 2026 (read directly, https://www.utilitydive.com/news/pjm-rto-large-load-interconnection-ferc-show-cause/874872/). PJM's cifp-lla page, re-read directly 2026-11-19 (navigation chrome only, no content change): https://www.pjm.com/committees-and-groups/cifp-lla. pjm.com/committees-and-groups/cifp-lla re-fetched directly 2026-11-20 (navigation chrome only, no content change).
Get an email when this changes
Other utilities in Ohio and Pennsylvania and New Jersey and Maryland and Virginia and Delaware and Illinois and Indiana and Kentucky and Michigan and North Carolina and Tennessee and West Virginia and DC
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.