Illinois (IL) data center power coverage

Real, sourced large-load tariff and interconnection research on file for Illinois — never inferred, never scraped, never implied beyond what's actually been checked.

Large-load tariffs

Commonwealth Edison (ComEd), large demand project applicants (Rider DE)

Approved Checked 2026-03-30
ThresholdProjected maximum kilowatts delivered of 50 MW or more before December of the 10th year after the requested service date
StatusLarge demand project applicants must post a deposit for analysis and engineering costs: $1,000,000, plus $500,000 for each additional whole 100 MW above 200 MW. Deposits above $2,000,000 require an acceptable letter of credit for the excess. Subject to the ICC investigation in dockets 25-0677/25-0679. SEPARATELY, not a ComEd/utility matter: Gov. Pritzker directed the Dept. of Commerce and Economic Opportunity (DCEO) to pause processing new agreements under the state's Data Center Investment Program (a state tax-incentive program, not a utility interconnection process) effective July 1, 2026 -- announced June 5, 2026, framed as part of a 2-year incentive suspension pending legislative study of cost/environmental impact. Existing agreements signed before July 1, 2026 are honored; this does not affect ComEd's Rider DE process above.
SourceComEd compliance filing, ICC Docket 25-0677/25-0679 (March 30 2026): https://www.icc.illinois.gov/downloads/public/filing/4/397281.pdf; Gov. Pritzker DCEO directive, announced June 5, 2026 (news coverage: eenews.net, stlpr.org; Governor's office primary text not directly located during this research).

Interconnection & regulatory guidance

Illinois — no statewide tariff law enacted yet; the POWER Act failed to advance in 2026

Contact guidanceComEd has its own detailed entry (Rider DE) if it serves the site -- this entry exists to record real statewide political context, not an adopted statewide rule.
ThresholdNot applicable -- nothing statewide is enacted yet. The POWER Act, as proposed, would have applied to hyperscale data centers over 50 MW.
ProcessThe POWER Act (SB 4016 / HB 5513), the most significant statewide data-center bill proposed in 2026, would have required a large-load tariff for data centers over 50 MW, mandated energy/capacity supply plans with local clean-energy investment, and required $2-12 million/year payments into an affordability fund. The Illinois General Assembly's 2026 regular session ended without advancing it. Separately, Gov. Pritzker paused new data-center tax incentives (announced June 5, 2026) and directed the General Assembly to revisit the issue during its veto session later in 2026 -- confirm whether that revisit produced any enacted change directly.
Deposit / costSeparately from the POWER Act, the Illinois Commerce Commission already approved a ComEd-specific proposal letting it require security deposits from large-load developers based on project energy needs -- covered in ComEd's own dedicated entry.
SourceCapitol News Illinois / NPR Illinois (nprillinois.org, capitolnewsillinois.com) coverage of the POWER Act's status and the ICC's ComEd deposit approval; Route Fifty (route-fifty.com) on the state being "not quite ready" to pass regulation as of mid-2026.

Land-constraint screening

Every Kill Test automatically screens against 6 nationwide land-constraint layers, Illinois included — no state-by-state gaps here.

FEMA Flood ZoneNearby WetlandsProtected / Conservation LandCritical HabitatSeismic HazardTribal Land
← Back to full coverage

Evaluating a specific parcel in Illinois?

Start a Qualification Review