Appalachian Power and Wheeling Power (West Virginia), Schedules LCP and IP large load terms

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-10-14
Applies at100 MW or more of new load or expansion at an individual site, or 150 MW or more aggregated
What the filing saysAPPROVED. West Virginia PSC Commission Order of March 25, 2025 (Case 24-0611-E-T-PW) accepted a Joint Stipulation and ordered revised Schedules LCP and IP. Does not apply to existing customers' contracted capacity as of Jan 1, 2025. Initial contract term of at least 12 years, and the customer may designate a load ramp of up to 5 years, after which the initial term starts. Monthly billing demand is the greater of 80% of contract capacity for that period or 80% of the highest billing demand in the past 11 months, with a minimum monthly charge. Collateral follows the companies' proposal (24 times the customer's monthly bill under the original proposal; the companies may negotiate a different amount). After 5 years the customer may cut contract capacity up to 20% in total with no exit fee on 42 months' written notice (before the start of a PJM delivery year); a larger cut or termination also needs 42 months' notice and an exit fee. The exit fee is reduced if capacity is reassigned. Collateral details come from the order's summary of the stipulation; the compliance tariff sheets were not read.

Stated terms

Contract term12 years after the ramp

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

WV PSC Commission Order, Case No. 24-0611-E-T-PW, March 25, 2025 (read in part: background, stipulation terms, ordering paragraphs); tariff sheets not read.