Coverage / Maryland

Maryland (MD) data center power coverage

Real, sourced large-load tariff and interconnection research on file for Maryland — never inferred, never scraped, never implied beyond what's actually been checked.

Large-load tariffs

Baltimore Gas and Electric (Maryland) -- large-load tariff under PSC Public Conference 72

Pending Checked 2026-10-14
Threshold25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
StatusBaltimore Gas and Electric (Maryland) -- large-load tariff under PSC Public Conference 72: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
SourceMaryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Pepco (Maryland) -- large-load tariff under PSC Public Conference 72

Pending Checked 2026-10-14
Threshold25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
StatusPepco (Maryland) -- large-load tariff under PSC Public Conference 72: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
SourceMaryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Potomac Edison (Maryland) -- large-load tariff under PSC Public Conference 72

Pending Checked 2026-10-14
Threshold25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
StatusPotomac Edison (Maryland) -- large-load tariff under PSC Public Conference 72: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
SourceMaryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Delmarva Power (Maryland) -- large-load tariff under PSC Public Conference 72

Pending Checked 2026-10-14
Threshold25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
StatusDelmarva Power (Maryland) -- large-load tariff under PSC Public Conference 72: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
SourceMaryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Southern Maryland Electric Cooperative (Maryland) -- large-load tariff required by state law

Pending Checked 2026-10-14
Threshold25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
StatusSouthern Maryland Electric Cooperative (Maryland) -- large-load tariff required by state law: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
SourceMaryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Interconnection & regulatory guidance

Maryland — statewide Utility Relief Act (large-load threshold lowered to 25 MW)

Contact guidanceNo dedicated Maryland utility large-load tariff is on file here yet (BGE, Pepco, Delmarva Power, SMECO, Potomac Edison each differ) -- contact the serving utility directly for interconnection process. Separately, as of 2026-10-08, every Maryland IOU/co-op is under a state-mandated deadline (below) to file large-load rate schedules.
ThresholdThe Utility Relief Act lowers the 'large load customer' threshold to 25 MW and a 60% load factor -- and separately redefines any data center as a large-load customer regardless of its demand or load factor, closing what would otherwise be a size-based exemption.
ProcessGov. Wes Moore signed the Utility Relief Act as emergency legislation on May 12, 2026. It requires every investor-owned electric utility and electric cooperative to file for Public Service Commission approval of specific large-load rate schedules -- the original Sept 1, 2026 filing deadline was extended to Jan 1, 2027. The Act also modifies an existing rate-schedule exemption for large-load customers who don't expand load more than 25 MW above existing contract capacity, specifically excluding data centers from that exemption, and requires utilities to pass PJM-assigned capacity costs through to large-load customers directly.
Deposit / costCost pass-through is explicit in the statute: PJM capacity costs assigned to a large-load account must be passed through to that customer, not socialized across the broader ratepayer base.
SourceUtility Relief Act, signed May 12, 2026 (Maryland General Assembly HB1082/legislative record, mgaleg.maryland.gov); Maryland Office of People's Counsel (OPC) comments filings (opc.maryland.gov) for the Jan 1, 2027 filing-deadline detail.

Land-constraint screening

Every Kill Test automatically screens against 6 nationwide land-constraint layers, Maryland included — no state-by-state gaps here.

FEMA Flood ZoneNearby WetlandsProtected / Conservation LandCritical HabitatSeismic HazardTribal Land
← Back to full coverage

Evaluating a specific parcel in Maryland?

Start a Qualification Review