| 1 | Kentucky Power Company, Tariff I.G.S. large load provisions KY | 18 |
| 20 yr | 90% | 24 months of minimum bills | 5 year(s) of minimum bills |
| 2 | Duke Energy Florida, proposed Large Load Customer Policy (Florida PSC)pending FL | 16 |
| 20 yr | 80% | Not stated | 3 year(s) of minimum bills |
| 3 | El Paso Electric (New Mexico), proposed Rate 50 High Load Factor Power Service and Rate 51 Large Load Power Servicepending NM | 16 |
| 20 yr | 80% | Not stated | Not stated |
| 4 | Florida Power & Light (LLCS-1 Large-Load Contract Service) FL | 14 |
| 20 yr | 70% | Not stated | Not stated |
| 5 | Consumers Energy (Rate GPD large-load / data center provision) MI | 12 |
| 15 yr | 80% | Not stated | Remaining minimum bills |
| 6 | Kentucky Utilities (Rate EHLF, Extremely High Load Factor Service) KY | 12 |
| 15 yr | 80% | 24 months of minimum bills | Remaining minimum bills |
| 7 | Louisville Gas & Electric (Kentucky), Rate EHLF Extremely High Load Factor Service KY | 12 |
| 15 yr | 80% | 24 months of minimum bills | Remaining minimum bills |
| 8 | Virginia Electric and Power Co. (Dominion Energy Virginia), GS-5 rate class VA | 11.9 |
| 14 yr | 85% | Not stated | Not stated |
| 9 | Appalachian Power Company (Virginia), Schedule L.P.S. large load terms VA | 11.2 |
| 14 yr | 80% | Not stated | Not stated |
| 10 | Colorado Springs Utilities (Colorado), Schedule ELL Industrial Service - Large Load CO | 10 |
| 10 yr | 100% | 36 months of minimum bills | Remaining minimum bills |
| 11 | Appalachian Power and Wheeling Power (West Virginia), Schedules LCP and IP large load terms WV | 9.6 |
| 12 yr | 80% | Not stated | Not stated |
| 12 | Evergy Kansas Central / Evergy Kansas South (Schedule LLPS) KS | 9.6 |
| 12 yr | 80% | Not stated | Not stated |
| 13 | Evergy Metro / Evergy Missouri West (Large Load Power Service, LLPS) MO | 9.6 |
| 12 yr | 80% | 24 months of minimum bills | Not stated |
| 14 | Indiana Michigan Power (AEP) IN | 9.6 |
| 12 yr | 80% | Not stated | Not stated |
| 15 | Union Electric Company d/b/a Ameren Missouri (Large Load Rate Plan) MO | 9.6 |
| 12 yr | 80% | 24 months of minimum bills | Not stated |
| 16 | Duke Energy Carolinas and Duke Energy Progress (North Carolina), proposed Large Load Tariff settlementpending NC | 7.5 |
| 10 yrlonger from 100 MW | 75% | Not stated | Not stated |
| 17 | AEP Ohio OH | 6.8 |
| 8 yr | 85% | Not stated | 3 year(s) of minimum bills |
| 18 | PPL Electric Utilities (Pennsylvania), Rate Schedule LP-6 large load / data center PA | 6.5 |
| 10 yr | 80% 50% after year 5 | Not stated | Remaining minimum bills |