Evergy Metro / Evergy Missouri West (Large Load Power Service, LLPS)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-03-09
Applies at75 MW or more of expected demand
What the filing saysMissouri PSC Report and Order (Case No. EO-2025-0154, Nov 13 2025), approving the Agreement's LLPS terms. Minimum service term of 12 years, plus an optional transitional load ramp of up to 5 years. The term starts when permanent service begins. Minimum demand of 80% of contract capacity. Collateral of two years of minimum monthly bills, with discounts for qualifying guarantors. Path to Power (Missouri West tariff, Rules section 2.10, effective Mar 9 2026): projects over 25 MW submit a refundable $200,000 planning deposit, plus another $200,000 if planning costs exceed it. Up to four projects are studied at a time. Deposit waiver only for community-interest projects (competitive search, 250+ jobs, economic development certification).

Stated terms

Contract term12 years after the ramp

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

Missouri PSC Report and Order, Case No. EO-2025-0154 (Nov 13 2025): https://efis.psc.mo.gov/Document/Display/857331; Evergy Missouri West P.S.C. MO. No. 1 (Rules 2.10; Schedule LLPS): https://psc.mo.gov/CMSInternetData/Community%20Outreach/Evergy%20Large%20Load%20Tariff.pdf