Northern States Power Co. (Xcel Energy Minnesota), very large customer tariffs

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-05-18
Applies atNew loads of 100 MW or greater; or 20 MW to under 100 MW if system intensive
What the filing saysMinnesota PUC decision (docket E-002/M-25-289, May 2026) approving Xcel's large-load tariffs. 15-year default contract term. Exit fee raised to 80% of contracted capacity. Xcel must create a separate large customer rate class for data centers.

Stated terms

Contract term15-year default contract term (PUC decision, May 2026)

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

Minnesota PUC bulletin, Very Large Customer requirements (May 2026): https://content.govdelivery.com/accounts/MNPUBUC/bulletins/417d139