Indiana Michigan Power (AEP)
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-10-14
Applies at70 MW single facility, or 150 MW aggregated
What the filing saysAPPROVED by the IURC (Cause 46097, settlement order February 19, 2025). Large Load Terms in Tariff I.P. apply to new load or expansions on or after January 1, 2024 at 70 MW or more at one site, or 150 MW aggregated (I&M has discretion over aggregation). Initial contract term of at least 12 years, starting after a load ramp period of up to 5 years. Minimum monthly billing demand of 80% of contract capacity or of the highest prior demand. Customers may reduce contract capacity by up to 20% during the term; larger reductions or termination trigger an exit fee. Higher collateral is required. A further proposal, Tariff IP-LL (Cause 46454), is pending. Below the threshold, standard Tariff I.P. applies.
Stated terms
Contract term12 years after the ramp
6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.
Source
IURC order in Cause 46097, February 19, 2025 (order text read in full).
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Indiana Michigan Power (AEP) territory
Get an email when this changes