Virginia Electric and Power Co. (Dominion Energy Virginia), GS-5 rate class

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2025-11-25
Applies at25 MW or greater on a contiguous site, and load factor of at least 75%
What the filing saysGS-5 rate class approved in Case PUR-2025-00058 (final order Nov 25, 2025): large loads are rated separately. Minimum demand charges of 85% of contracted demand for distribution and transmission, and 60% for generation. Contract term of 14 years for customers signing an ESA on or after Jan 1, 2027, with a load ramp period of up to 4 years. Collateral of $1.5 million per MW, reducible by up to 70% based on the customer's credit; third-party guarantees and letters of credit are allowed. Cash collateral earns interest.

Stated terms

Contract term14 years (includes the ramp)

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

https://www.scc.virginia.gov/docketsearch/DOCS/89g601!.PDF (final order, Case PUR-2025-00058)