Southwestern Electric Power Company (SWEPCO, Texas), proposed Large Load standard contract
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusPending Last reviewed 2026-10-14
Applies at75 MW or more of contract capacity at one facility or in aggregate (EEI summary)
What the filing saysPENDING, WITH A SETTLEMENT FILED. PUCT Docket 58796: SWEPCO applied for a new standard form contract for large load electric service (ES-LL Contract). The docket lists a Unanimous Stipulation and Settlement Agreement. The stipulation and contract terms were not read, and no final order was confirmed.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
PUCT Interchange docket 58796 index; EEI list, Sept 2026.
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Southwestern Electric Power Company (SWEPCO territory
Get an email when this changes
Other utilities in Texas
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.