Kentucky Power Company, Tariff I.G.S. large load provisions
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-10-14
Applies at150 MW or more of new load, or of incremental load added by an existing customer, on or after the order date
What the filing saysAPPROVED. Kentucky PSC Order in Case 2024-00305 (the EEI list dates the approval March 2025) approved Kentucky Power's revisions to Tariff I.G.S. as modified: they apply only to customers adding 150 MW or more of incremental load. Provisions as filed and approved: 20-year contract term with 5 years' notice to terminate; minimum monthly billing demand of at least 90% of the customer's highest established demand; collateral of 24 times the customer's previous maximum monthly non-fuel bill (subject to review and adjustment); a one-time payment equal to 5 years of minimum billing if the customer permanently closes before the term ends; 5 years' notice to reduce contract capacity, with exceptions by mutual agreement. The compliance tariff sheets were not read.
Stated terms
Contract term20 years
6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.
Source
Kentucky PSC Order, Case No. 2024-00305 (psc.ky.gov, read in full; the order date was not captured).
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Kentucky Power Company territory