PPL Electric Utilities (Pennsylvania), Rate Schedule LP-6 large load / data center
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-10-14
Applies at50 MW or more at a single facility, or 75 MW or more in aggregate at 69 kV or above within a 10-mile radius
What the filing saysPA PUC approved the rate settlement in Docket R-2025-3057164 on June 4, 2026; compliance tariff for service on and after July 1, 2026. Applies to customers whose service began on or after Oct 1, 2025. Every LP-6 customer signs an Electric Service Agreement (ESA) and takes transmission-level service (69 kV or above). Initial term at least 10 years, with a load ramp of up to 5 years. Pay the greater of actual peak demand or 80% of the ramp schedule until the customer has paid transmission revenue equal to its Rate Base Security Obligation; after that, 80% for years 1-5 and 50% for years 6-10. A voluntary interruptible option cuts those minimums to 60% and 30%. Security (letter of credit, parent guarantee or similar) equals the cost of upgrades needed to serve the customer. Exit fee is the larger of the remaining minimum-load obligation or the remaining Rate Base Security Obligation. Up-front construction payments (CIAC) for directly assigned upgrades. A single facility of 50 to 75 MW with no transmission network upgrades may petition to stay on Rate LP-5. These terms come from the settlement terms quoted in the Commission's recommended decision; the final compliance tariff sheet was not read.
Stated terms
Contract term10 years after the ramp
6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.
Source
PA PUC recommended decision in R-2025-3057164 (puc.pa.gov/pcdocs/1923934.pdf, terms read); PA PUC press release of June 4, 2026. The state-wide model framework is a separate row.
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in PPL Electric Utilities (Pennsylvania) territory
Get an email when this changes
Other utilities in Pennsylvania
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.