MISO

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-11-02
Applies atLoads above 200 MW paired with generation holding a firm offtake agreement in the same MISO local resource zone (as proposed)
What the filing saysPENDING at FERC. Reported (Utility Dive, Ethan Howland, Oct 26, 2026; FERC filing itself not read): MISO proposed the Large Load Addition Resource Study (LARS), a 120-day fast-track combined interconnection study for large loads above 200 MW paired with generation (holding a firm offtake agreement) in the same MISO local resource zone, open only to MISO's transmission customers -- mainly its vertically integrated load-serving utilities. MISO says it responds partly to FERC's mid-June 2026 finding that MISO's large-load rules were inadequate. Supporting: Duke Energy Indiana, Entergy utilities, Cleco Power and other MISO transmission owners (who want it made permanent, citing 15 years of regulatory/financial certainty); the Data Center Coalition supports it generally but objects to load-serving-entity-only access. Opposing: the Organization of MISO States (OMS) says a majority of its members have 'significant concerns,' backed by 11 state commissions; ratepayer advocates for six states, Google, and a coalition including the Sierra Club and NRDC oppose it, chiefly over transmission cost-shifting to existing customers. Arkansas, Louisiana and Mississippi's commissions voted against OMS's critical comments and filed in support of MISO's plan instead. MISO has said it will file a separate cost-allocation framework for LARS projects; Google says that framework's details remain open questions FERC cannot assume away. No FERC ruling found as of this research.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Utility Dive, 'Dive Brief' by Ethan Howland, Oct 26, 2026 (read directly, https://www.utilitydive.com/news/miso-large-load-lars-ferc-google-oms/849887/). FERC docket and filings not read.

Get an email when this changes

Other utilities in Arkansas and Iowa and Illinois and Indiana and Louisiana and Michigan and Minnesota and Mississippi and Missouri and Montana and North Dakota and South Dakota and Texas and Wisconsin

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.