Coverage / Iowa

Iowa (IA) data center power coverage

Real, sourced large-load tariff and interconnection research on file for Iowa — never inferred, never scraped, never implied beyond what's actually been checked.

Large-load tariffs

Interstate Power and Light (Alliant Energy Iowa), Rider ICR Individual Customer Rate

Approved Checked 2026-10-14
Threshold25 MW or more (25,000 kW) at a single metering point, served at 69 kV or above, with an expected 80% load factor and 175,000 MWh a year, or demonstrated ability to curtail to a firm demand level
StatusRider ICR (Substitute Sixth Revised Sheet No. 80, effective Oct 1, 2024) is available only under a written Service Agreement and at IPL's discretion: IPL can decline a customer it judges uneconomic or constrained by generation or transmission. Customers should tell IPL a year before service. The Service Agreement is filed with the Iowa Utilities Commission at least 90 days before service and needs its approval. Minimum term is 5 years, and a longer term can be required. Demand and energy rates are negotiated, but no lower than IPL's expected incremental cost of serving the customer; energy up to a baseline demand can be priced at a fixed or marginal (MISO node) price. Customers not served at transmission voltage pay for the distribution facilities needed. The sheet states no take-or-pay percentage, exit fee or collateral; those terms sit in each Service Agreement. Two agreements are on file as examples (Vulpine Power, TF-2025-0007; QTS, TF-2025-0047). MidAmerican is not covered by this row.
Contract termMinimum term of 5 years; a longer term can be required (Rider ICR)
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNot stated in the filings we read
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceIPL Rider ICR tariff sheets 80-82 (Alliant Energy, read in full); EEI Large Load Projects and Tariffs, Sept 2026, for the agreement docket numbers (not independently opened).

MidAmerican Energy (Iowa) -- no large-load tariff found

None found Checked 2026-10-14
ThresholdNo Iowa large-load tariff found for MidAmerican
StatusNo MidAmerican large-load tariff was found, and no primary source was read for it. Treat as unknown and ask the utility.
SourceNot read. Carried over from the earlier Iowa row.

Interconnection & regulatory guidance

Utility-specific — no statewide guidance resolves without naming a utility, but real tariff research exists above for Interstate Power and Light (Alliant Energy Iowa), Rider ICR Individual Customer Rate and MidAmerican Energy (Iowa) -- no large-load tariff found. Interconnection process for a specific utility can be confirmed directly once that utility is identified for your site.

Land-constraint screening

Every Kill Test automatically screens against 6 nationwide land-constraint layers, Iowa included — no state-by-state gaps here.

FEMA Flood ZoneNearby WetlandsProtected / Conservation LandCritical HabitatSeismic HazardTribal Land
← Back to full coverage