Tennessee Valley Authority (data center rate / Capacity Commitment Charge)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-08-20
Applies atNew or expanding loads above 5 MW
What the filing saysNew standard data center rate effective Oct 1, 2026, approved at the Aug 20, 2026 TVA Board meeting. A Capacity Commitment Charge (CCC) applies to new or expanding loads above 5 MW as part of each data center B, C, and D rate schedule, to recover incremental capacity costs. All-in average billing impact to data center customers is expected to be about 10%, phased in over three consecutive fiscal years. A Power Interruption Provision sets terms for a data center that wants to come online before its generation capacity is available. In-flight data centers must meet specific criteria to qualify for transitional provisions (criteria not detailed in this deck). Separately, the Board updated its policy for new power requirements above 100 MW. The CCC's exact dollar amount or formula was not found in this deck.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

TVA Board presentation, Aug 20, 2026 meeting (read directly): https://tva-azr-eastus-cdn-ep-tvawcm-prd.azureedge.net/cdn-tvawcma/docs/default-source/about-tva/board-of-directors/august-20--2026/august-2026-board-presentation.pdf

Get an email when this changes

Other utilities in Tennessee and Alabama and Georgia and Kentucky and Mississippi and North Carolina and Virginia

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.