East Kentucky Power Cooperative, Rate DCP Data Center Power
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-10-14
Applies atData center with an expected or actual peak of 15,000 kW (15 MW) or more and a monthly load factor of 60% or more; loads over 250 MW must be served with dedicated resources
What the filing saysAPPROVED as modified (Kentucky PSC Order, Case 2025-00140, issued after Oct 20, 2025). Rate DCP sets the rules under which EKPC and its member cooperatives serve data centers. Each data center signs a special contract with EKPC and the member cooperative that the PSC must approve; the contract sets term, contract capacity and load ramp, rates, any minimum billing demand, curtailment, default and termination terms. EKPC and the member must settle a power supply plan first (dedicated resources, bilateral purchases, or both) and will not start service until the resource mix is secured. Service runs through PJM markets. All costs of serving the data center are allocated to it. Loads over 250 MW require dedicated resources and the Dedicated Resource Rider. Specific percentages and years are in each contract, not the tariff.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
Kentucky PSC Order, Case No. 2025-00140 (psc.ky.gov, read in part: description of the tariff and the ordering paragraphs).
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in East Kentucky Power Cooperative territory