Duke Energy Carolinas and Duke Energy Progress (North Carolina), Large Load Tariff
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-11-20
Applies atData-center-specific rate conditions apply to data centers using more than 50 MW (confirmed by NPR/WFAE, Nov 18, 2026, reported); the settlement as filed also proposed a 150 MW-aggregate alternative test, not independently reconfirmed against the final order
What the filing saysAPPROVED (reported, order text not read). NCUC Dockets E-7 Sub 1329 (Duke Energy Carolinas) and E-2 Sub 1380 (Duke Energy Progress): multiple outlets (Axios, Nov 17, 2026; Crypto Briefing, Nov 17, citing Duke Energy's own release; WFAE/WUNC, Nov 18, byline Zachary Turner, with named-source quotes and an excerpt from Commissioner Donald van der Vaart's dissent) report the Commission approved new base rates for both utilities (effective Jan 1, 2027, in two annual steps) together with new data-center-specific rate conditions, around Nov 16-17, 2026. Per WFAE/WUNC (reported): rather than adopting Duke's and the data-center developers' proposed tariff as filed, 'the commission decid[ed] to go their own way on how they want to deal with these large load customers' (quoting Matt Abele, NC Sustainable Energy Association); the new rate conditions apply only to data centers using over 50 MW, require them to pay more of the transmission, distribution and interconnection cost of serving them, and keep 'many of the hallmarks' of Duke's proposed tariff -- minimum contract lengths, early-termination fees and other provisions -- plus a new, previously-unreported 'stranded generation charge': collateral (a letter of credit or similar) equal to the remaining useful life of the new gas-fired generation built to serve the load, tied to the gap between the 10-15 year minimum contract length and the roughly 35-year useful life of the new turbines (so a 15-year contract leaves about 20 years of value to be secured). Commissioner van der Vaart dissented, writing the mismatch is 'like financing a house over 35 years for a tenant who promises to stay only 15.' Separately, the same orders approved $20 million of shareholder-funded customer assistance and are reported to approve roughly 3.4%-3.7% (Crypto Briefing) or up to 5.9% (WFAE) average annual rate increases depending on utility and customer class; those residential-rate figures are not large-load terms and are noted only for context. None of this agent's attempts reached the NCUC's own docket site (starw1.ncuc.gov returned HTTP 403 directly, and the fetch relay returned 'URL not allowed' for it, so the actual order text was not opened); the settlement's previously-modeled specific numbers (75% minimum billing demand, the 24/36/48-month notice tiers, the exact termination-damages formula) are therefore NOT reconfirmed and may not be what the Commission actually adopted, given the reporting's explicit statement that the Commission did not simply adopt the settlement. This resolves the Nov 17, 2026 'UNCONFIRMED' TheEnergyMag headline noted in the prior version of this entry (and the matching backlog item) -- the underlying event is now confirmed by multiple named, bylined outlets, even though the order itself remains unread. South Carolina has a separate generic docket (2026-138-E), not addressed by this NC order; see that state's own row above.
Stated terms
Contract termReported as 10 to 15 years (NPR/WFAE, Nov 18, 2026, quoting a dissenting commissioner that data-center contracts run 15 years); the order itself was not read, so which size threshold triggers which length is NOT confirmed to be what the Commission adopted.
6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them.
Source
Agreement and Stipulation of Settlement on Large Load Tariff, filed Oct 6, 2026 (SELC-hosted copy, read in full) -- superseded in part by the Commission's own order, which reporting says departs from it; Axios, 'N.C. regulators approve Duke Energy rate increase' (axios.com, Nov 17, 2026, read); Crypto Briefing, 'Duke Energy wins North Carolina approval for rate increases and large data-center tariff' (cryptobriefing.com, Nov 17, 2026, read in full, citing Duke Energy's own release); WFAE/WUNC, 'NC regulators approve new rates for data centers in rate hike plan' (wfae.org/wunc.org, by Zachary Turner, Nov 18, 2026, read in full). NCUC's own order text in E-7 Sub 1329 / E-2 Sub 1380 was not read (starw1.ncuc.gov returned HTTP 403 to a direct fetch 2026-11-20; the agent fetch relay returned 'URL not allowed' for that host).
Get an email when this changes
Other utilities in North Carolina
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.