Taylor County RECC (Rate DCP Data Center Power; Schedules B1-B3 and C1-C3 Large Industrial)
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2026-11-13
Applies atRate DCP: an eligible Data Center as defined in EKPC's Rate DCP (15 MW or more at a monthly load factor of 60% or more); Schedules B1-B3/C1-C3: contracts of 500 kW and up with at least 400 hours of use per kW
What the filing saysAPPROVED. Taylor County RECC's own Rate DCP (Original Sheet No. 167, issued April 30, 2026, effective service on and after June 1, 2026) is available in all territory served to any retail customer that owns or proposes to own an eligible Data Center as defined in EKPC's Rate DCP (PSC No. 35, Original Sheet 103, Section III). Before service the customer negotiates a contract with the cooperative and EKPC that follows EKPC's Rate DCP Sections IV to VIII; the contract sets the rates (revised over time as the PSC determines), added to any applicable riders (fuel adjustment, Rate ES environmental surcharge, Rate D interruptible, Rate H, power factor adjustment). The PSC must approve the contract terms before service. EKPC and the cooperative may deviate from the tariff for good cause with PSC approval. Term, ramp, minimum billing and collateral are in EKPC's Rate DCP and each contract, not in the cooperative's sheet. Standard large industrial schedules (reissued May 1, 2026 under PSC Case 2025-00209, order of April 28, 2026): B1 500-4,999 kW consumer charge $1,362.55, demand $6.87/kW of contract demand ($9.96/kW in excess), energy $0.06719/kWh; B2 5,000-9,999 kW $3,228.61, $6.87, $0.06172; B3 10,000 kW and over $3,851.58, $6.87, $0.060437; C1-C3 (two-party contracts) $1,376.36/$3,205.45/$3,823.95 consumer charge, $6.94/kW, $0.06787/$0.06128/$0.060004 per kWh. B-schedule minimum bill is the consumer charge plus contract demand charges plus contract demand times 400 hours times the energy charge, plus any special-facilities terms; fuel adjustment (up to 10% line-loss allowance) applies. Whether a given site is served by this cooperative is the site owner's statement until confirmed with the cooperative.
Stated terms
Contract termNot stated in the filings we read
6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them.
Source
Taylor County RECC tariff book, PSC KY No. 5 (psc.ky.gov, Rate DCP Sheet 167 and Schedules B1-B3, C1-C3 read in full); EKPC Rate DCP is read in part under the EKPC row.
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Taylor County RECC (Rate DCP Data Center Power; Schedules B1-B3 and C1-C3 Large Industrial) territory
Get an email when this changes
Other utilities in Kentucky
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.