Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Kentucky Power Company, Tariff I.G.S. large load provisions
StatusApproved
Applies at150 MW or more of new load, or of incremental load added by an existing customer, on or after the order date
Last reviewed2026-10-14
Contract term20 years
RampNot stated in the filings we read
Take-or-pay (minimum bill)90% of contract capacity billed monthly whether used or not
Collateral24 months of minimum bills
Exit fee5 years of minimum bills
Notice to reduce or end60 months
Time to powerNot stated in the filings we read
SourceKentucky PSC Order, Case No. 2024-00305 (psc.ky.gov, read in full; the order date was not captured).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site