Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| East Kentucky Power Cooperative, Rate DCP Data Center Power | |
|---|---|
| Status | Approved |
| Applies at | Data center with an expected or actual peak of 15,000 kW (15 MW) or more and a monthly load factor of 60% or more; loads over 250 MW must be served with dedicated resources |
| Last reviewed | 2026-10-14 |
| Contract term | Not in structured terms yet; see the source |
| Ramp | Not in structured terms yet; see the source |
| Take-or-pay (minimum bill) | Not in structured terms yet; see the source |
| Collateral | Not in structured terms yet; see the source |
| Exit fee | Not in structured terms yet; see the source |
| Notice to reduce or end | Not in structured terms yet; see the source |
| Time to power | Not in structured terms yet; see the source |
| Source | Kentucky PSC Order, Case No. 2025-00140 (psc.ky.gov, read in part: description of the tariff and the ordering paragraphs). |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site