Northern Virginia Electric Cooperative (NOVEC), Schedule HV-1 Large Power Dedicated Distribution Service

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-10-14
Applies atNew or additional separately metered load of at least 5,000 kW (5 MW), with an average annual load factor of at least 70%, served at 115 kV or higher
What the filing saysIN EFFECT (Schedule HV-1 effective April 1, 2023; the SCC docket lists changes to HV-1 and a larger HV-2 dedicated facilities schedule as pending, and those changes were not read). The customer signs an electric service agreement at least 12 months before service. The term is negotiable but structured to recover the full cost of distribution and sub-transmission plant; the customer contributes in aid of construction for primary distribution facilities and may buy power from NOVEC (standard or market option) or from a third-party provider. Not available for backup or standby service.

Stated terms

Contract termNegotiable but structured to recover the full cost of distribution and sub-transmission plant; the length is in the agreement, not the schedule

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

NOVEC Schedule HV-1, effective 4/1/2023 (novec.com, read).