NIPSCO GenCo (Indiana), megaload service through a separate generation company

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-10-14
Applies atA 'megaload' customer is 50 MW or more under the approved settlement (a consumer group argued for 100 MW)
What the filing saysSTRUCTURE APPROVED by the IURC in Cause 46183 (order of September 24, 2025): a limited declination of jurisdiction lets NIPSCO GenCo, a ring-fenced affiliate, build and own generation that NIPSCO then contracts for to serve megaload customers, so the cost does not fall on NIPSCO's other customers. The order does not set contract terms; power purchase agreements and special contracts with megaload customers are reviewed case by case. NIPSCO says contracts use minimum terms, minimum load factors and exit fees. No published megaload term sheet was found.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

IURC order in Cause 46183, September 24, 2025 (in.gov/iurc, read in part).