Louisiana PSC Private Use Electrical Network (PEN) rule (Docket R-37905)
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusPending Last reviewed 2026-11-18
Applies atStaff's proposed rule: new industrial or digital load of 50 MW or more operating at an 80% or higher average monthly load factor
What the filing saysPENDING -- a state-wide rulemaking on self-supply, not a utility tariff. Docket No. R-37905 (opened to determine and evaluate Private Use Electrical Networks, 'in order to enable generation to serve new large loads looking to locate in Louisiana') is a generic LPSC rulemaking, separate from any one utility's tariff. LPSC Staff's Final Report and Recommendation (filed Nov 4, 2026, read in full via pdftotext) proposes rules letting a Private Use Electrical Network (PEN, previously called a PUEN) serve a customer's new industrial or digital load of 50 MW or more with at least an 80% average monthly load factor, provided at least 85% of the PEN's capacity value and 70% of its energy output is dedicated to serving that identified customer load; existing load already on the public grid would not be permitted to exit onto a PEN; and the rule carries a five-year sunset subject to renewal if the Commission finds renewal serves the public interest. This expands Staff's simpler Aug 14, 2026 Initial Proposed Rule (about 11 pages) into a roughly 30-page Final Proposed Rule after a stakeholder comment period that closed Sept 25, 2026. A joint letter from the Louisiana Energy Users Group, the Louisiana Chemistry Association and the Louisiana Mid-Continent Oil & Gas Association (filed Nov 16, 2026, read in full) opposes the Final Proposed Rule's form as too complex and commercially unworkable, and instead urges the Commission to adopt Staff's simpler Aug 14 Initial Proposed Rule with the limited edits industry submitted Sept 25, 2026; the letter frames a PEN as simply allowing self-supply through a purchase-power agreement, in addition to the ownership or lease structures already allowed under existing Louisiana law (La. R.S. 45:121). The Final Proposed Rule was Agenda Exhibit 2 for the LPSC's Nov 18, 2026 Business & Executive Session (the same day as this research); no Commission vote or order was available to check as of this entry.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
LPSC Docket R-37905: Staff's Final Report and Recommendation Containing Staff's Final Proposed Rules (filed Nov 4, 2026, read in full via pdftotext), lpscpubvalence.lpsc.louisiana.gov; Correspondence to Oppose the Form of the Final Proposed Rules for Private Use Electrical Networks, filed on behalf of the Louisiana Energy Users Group/Louisiana Chemistry Association/Louisiana Mid-Continent Oil & Gas Association (filed Nov 16, 2026, read in full via pdftotext), same docket.