Entergy Louisiana (Schedule LLHLFPS-L, Large Load High Load Factor Power Service)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-10-17
Applies at70 MW or more of firm load, with at least an 80% average monthly load factor
What the filing saysCommission-approved rate schedule (LPSC Order U-36959; revision effective Aug 30, 2024). Applies to customers contracting for not less than 70 MW of firm load with facilities operating at an 80% average monthly load factor. Read in full from Entergy's rate schedule PDF on 2026-10-17: the contract is for a minimum of five years and, at the company's option, may be longer to justify the investment in generation and transmission facilities; the minimum bill is not less than the sum of the first and second demand blocks, and if the average of the maximum demands over the preceding twelve months falls below 70 MW, the current month's demand is raised to bring that average up to 70 MW; where facilities are not adjacent the company may require a contribution, a higher minimum bill or a facilities charge. Collateral, ramp and exit terms are not in the schedule; other terms are in the ESA and riders. SEPARATELY, not an Entergy/LPSC matter: Gov. Landry's executive order (June 26, 2026) directs Louisiana Economic Development Secretary Susan Bourgeois to draft, within 90 days, new requirements a data center must meet to claim the state's Data Center Sales and Use Tax Exemption, balancing investor interest against Louisiana ratepayers' electricity costs. Not a moratorium -- Landry explicitly framed it as pro-development with guardrails.

Stated terms

Contract termMinimum of five years, and longer at the company's option to justify the investment in generation and transmission facilities (Schedule LLHLFPS-L, Section VII)

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

Entergy Louisiana rate schedule LLHLFPS-L PDF (read in full 2026-10-17); https://www.entergylouisiana.com/wp-content/uploads/ell_elec_llhlfps-l.pdf (filed tariff, LPSC Order U-36959); Gov. Landry executive order, announced June 26 2026 (news coverage: wafb.com, lailluminator.com, news.bloombergtax.com; Governor's office primary text not directly located during this research).