Cleco Power (Louisiana), Large Power Service and the Delta Forge data center contract

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusLaw or process only  Last reviewed 2026-10-14
Applies atLarge Power Service starts at 5,000 kW; the LPSC's large-load guidelines are non-binding and set no MW trigger
What the filing saysLOWER CONFIDENCE. Cleco's general Large Power Service (LPSC Tariff No. 7, revised January 1, 2026) requires at least 5,000 kW under an Agreement for Service, with a $10,000 customer charge and a billing demand charge; it is not data-center-specific. The LPSC's Large Load Additions Guidelines (docket X-37921, comments due June 19, 2026) are non-binding. Cleco filed July 1, 2026 for approval of an electric service agreement with Applied Digital for the Delta Forge site, new gas generation and a temporary capacity agreement; on September 16 the LPSC moved it forward without an ALJ recommendation. Contract terms are not public. Entergy Louisiana has its own approved schedule in a separate row.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Cleco Large Power Service tariff PDF (cleco.com, summary); LPSC and local news coverage of the Applied Digital filing; contract not read.

Get an email when this changes

Other utilities in Louisiana

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.