Free tool
Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Indiana Michigan Power (AEP) | |
|---|---|
| Status | Approved |
| Applies at | 70 MW single facility, or 150 MW aggregated |
| Last reviewed | 2026-10-14 |
| Contract term | 12 years after the ramp |
| Ramp | Up to 5 years |
| Take-or-pay (minimum bill) | 80% of contract capacity billed monthly whether used or not |
| Collateral | Not stated in the filings we read |
| Exit fee | Not stated in the filings we read |
| Notice to reduce or end | Not stated in the filings we read |
| Time to power | Not stated in the filings we read |
| Source | IURC order in Cause 46097, February 19, 2025 (order text read in full). |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site