Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Entergy Louisiana (Schedule LLHLFPS-L, Large Load High Load Factor Power Service)
StatusApproved
Applies at70 MW or more of firm load, with at least an 80% average monthly load factor
Last reviewed2026-10-17
Contract termMinimum of five years, and longer at the company's option to justify the investment in generation and transmission facilities (Schedule LLHLFPS-L, Section VII)
RampNot stated in the filings we read
Take-or-pay (minimum bill)Minimum bill of not less than the sum of the first and second demand blocks; if the average of the maximum demands over the preceding twelve months falls below 70 MW, demand is raised to bring that average up to 70 MW (Section IV.B)
CollateralNot stated in the filings we read
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceEntergy Louisiana rate schedule LLHLFPS-L PDF (read in full 2026-10-17); https://www.entergylouisiana.com/wp-content/uploads/ell_elec_llhlfps-l.pdf (filed tariff, LPSC Order U-36959); Gov. Landry executive order, announced June 26 2026 (news coverage: wafb.com, lailluminator.com, news.bloombergtax.com; Governor's office primary text not directly located during this research).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site