Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Northern States Power Co. (Xcel Energy Minnesota), very large customer tariffs
StatusApproved
Applies atNew loads of 100 MW or greater; or 20 MW to under 100 MW if system intensive
Last reviewed2026-05-18
Contract term15-year default contract term (PUC decision, May 2026)
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNot stated in the filings we read
Exit feeExit fee raised to 80% of contracted capacity (PUC decision, May 2026)
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceMinnesota PUC bulletin, Very Large Customer requirements (May 2026): https://content.govdelivery.com/accounts/MNPUBUC/bulletins/417d139

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.