Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Duke Energy Carolinas and Duke Energy Progress (North Carolina), Large Load Tariff
StatusApproved
Applies atData-center-specific rate conditions apply to data centers using more than 50 MW (confirmed by NPR/WFAE, Nov 18, 2026, reported); the settlement as filed also proposed a 150 MW-aggregate alternative test, not independently reconfirmed against the final order
Last reviewed2026-11-20
Contract termReported as 10 to 15 years (NPR/WFAE, Nov 18, 2026, quoting a dissenting commissioner that data-center contracts run 15 years); the order itself was not read, so which size threshold triggers which length is NOT confirmed to be what the Commission adopted.
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNEW, not in the Oct 6 settlement as previously summarized here: reported 'stranded generation charge' -- if a data center's contract runs 15 years, the developer must post a letter of credit or similar collateral equal to the remaining ~20 years of useful life of the new gas-fired capacity built to serve it (new turbines are described as having a 35-year useful life); if the data center leaves after 15 years it pays that remaining value (NPR/WFAE, reported, order not read).
Exit feeEarly-termination fees and minimum contract lengths are reported to carry over from Duke's proposed tariff, but the exact termination-damages formula was NOT confirmed against the final order and may not be what the Commission adopted.
Notice to reduce or endNotice-to-leave tiers (previously modeled here as 24/36/48 months by size, per the Oct 6 settlement as filed) were NOT confirmed against the final order.
Time to powerNot stated in the filings we read
SourceAgreement and Stipulation of Settlement on Large Load Tariff, filed Oct 6, 2026 (SELC-hosted copy, read in full) -- superseded in part by the Commission's own order, which reporting says departs from it; Axios, 'N.C. regulators approve Duke Energy rate increase' (axios.com, Nov 17, 2026, read); Crypto Briefing, 'Duke Energy wins North Carolina approval for rate increases and large data-center tariff' (cryptobriefing.com, Nov 17, 2026, read in full, citing Duke Energy's own release); WFAE/WUNC, 'NC regulators approve new rates for data centers in rate hike plan' (wfae.org/wunc.org, by Zachary Turner, Nov 18, 2026, read in full). NCUC's own order text in E-7 Sub 1329 / E-2 Sub 1380 was not read (starw1.ncuc.gov returned HTTP 403 to a direct fetch 2026-11-20; the agent fetch relay returned 'URL not allowed' for that host).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site