Southern Maryland Electric Cooperative (Maryland)
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusPending Last reviewed 2026-10-14
Applies at25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
What the filing saysSouthern Maryland Electric Cooperative (Maryland) -- large-load tariff required by state law: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
Maryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Southern Maryland Electric Cooperative (Maryland) territory
Get an email when this changes
Other utilities in Maryland
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.