Baltimore Gas and Electric (Maryland)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-10-14
Applies at25 MW and 60% load factor (per the Utility Relief Act); any data center regardless of size or load factor
What the filing saysBaltimore Gas and Electric (Maryland) -- large-load tariff under PSC Public Conference 72: The Utility Relief Act (signed May 12, 2026) requires every Maryland investor-owned electric utility and electric cooperative to file large-load rate schedules with the PSC. Sources conflict on the filing date: the bill record we read says January 1, 2027, while an October 2026 law-firm commentary says the September 1, 2026 filing deadline has passed and the dispute has moved to the filed tariff sheets (PSC Public Conference 72). The utilities' own tariff terms (minimum bills, contract terms, collateral) were NOT read, so treat contract terms as unknown and confirm with the utility.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Maryland General Assembly HB1082/legislative record (mgaleg.maryland.gov); Maryland OPC filings (opc.maryland.gov); law-firm commentary dated Oct 5, 2026 (mintz.com). Utility tariff sheets not read.

Get an email when this changes

Other utilities in Maryland

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.