Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| PPL Electric Utilities (Pennsylvania), Rate Schedule LP-6 large load / data center | |
|---|---|
| Status | Approved |
| Applies at | 50 MW or more at a single facility, or 75 MW or more in aggregate at 69 kV or above within a 10-mile radius |
| Last reviewed | 2026-10-14 |
| Contract term | 10 years after the ramp |
| Ramp | Up to 5 years |
| Take-or-pay (minimum bill) | 80% of contract capacity billed monthly whether used or not; 50% after year 5 |
| Collateral | Not stated in the filings we read |
| Exit fee | Remaining minimum bills for the rest of the term |
| Notice to reduce or end | Not stated in the filings we read |
| Time to power | Not stated in the filings we read |
| Source | PA PUC recommended decision in R-2025-3057164 (puc.pa.gov/pcdocs/1923934.pdf, terms read); PA PUC press release of June 4, 2026. The state-wide model framework is a separate row. |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site