Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

PPL Electric Utilities (Pennsylvania), Rate Schedule LP-6 large load / data center
StatusApproved
Applies at50 MW or more at a single facility, or 75 MW or more in aggregate at 69 kV or above within a 10-mile radius
Last reviewed2026-10-14
Contract term10 years after the ramp
RampUp to 5 years
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not; 50% after year 5
CollateralNot stated in the filings we read
Exit feeRemaining minimum bills for the rest of the term
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourcePA PUC recommended decision in R-2025-3057164 (puc.pa.gov/pcdocs/1923934.pdf, terms read); PA PUC press release of June 4, 2026. The state-wide model framework is a separate row.

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site