Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Evergy Metro / Evergy Missouri West (Large Load Power Service, LLPS)
StatusApproved
Applies at75 MW or more of expected demand
Last reviewed2026-03-09
Contract term12 years after the ramp
RampUp to 5 years
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not
Collateral24 months of minimum bills
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceMissouri PSC Report and Order, Case No. EO-2025-0154 (Nov 13 2025): https://efis.psc.mo.gov/Document/Display/857331; Evergy Missouri West P.S.C. MO. No. 1 (Rules 2.10; Schedule LLPS): https://psc.mo.gov/CMSInternetData/Community%20Outreach/Evergy%20Large%20Load%20Tariff.pdf

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.