Spartanburg County Signed $1.2 Billion in New Data Centers This Week. Its Last Deal Is Why the Rules Just Changed.
Spartanburg County approved $1.2 billion in new data centers this week and banned the power-plant workaround its last big project used -- then signed a 10-year deal protecting that same project from the ban.
Nine months ago, Spartanburg County, South Carolina killed a data center. In February, TigerDC's Project Spero ran into enough backlash that the county council signaled it would reject the company's tax incentive, and TigerDC pulled the project out of Tyger River Industrial Park the very next day. On November 16th, the same industrial park got three new data center agreements approved in a single meeting, and one of them carries a familiar name behind it. AIB CLT1, LLC is led by Jerry Tang, the same executive who ran TigerDC.
AIB's project is a conversion, not a new build: a crypto-mining data center on Tyger River Industrial Drive that was de-energized in June, after falling bitcoin prices made running its 40 megawatts of mining rigs unprofitable, is being rebuilt as two 25-megawatt AI data halls. AIB has already signed a 12-year colocation contract with the AI cloud company Nebius to fill them, targeting completion in the fourth quarter of 2027, on a reported $1.2 billion investment. The county council approved AIB CLT1's development agreement unanimously, alongside a second agreement for 300 Jones Road Associates, and advanced three more AIB proposals for the same industrial park (CLT2, CLT3, and CLT4) on their first reading, also unanimously.
The dollar figures council members cited add up fast. AIB CLT1's agreement alone commits $12.6 million in community-benefit payments over 12 years. Taken together, county officials put the combined community-benefit total for the five agreements moving through council this month at roughly $60 million, against roughly $100 million in local tax incentives. For a county that spent February watching its last big data center deal collapse in public, that's a real reversal, and whatever one thinks of the trade, it is a specific, checkable number instead of a press-release projection.
AIB's site is also a specific kind of conversion worth naming: a crypto-mining operation that stopped making sense once bitcoin prices fell, retrofitted for an AI tenant instead of demolished or left idle. It's the same pivot behind Anthropic's $28 billion lease of Riot Platforms' bitcoin-mining site in Corsicana, Texas, and it's becoming a pattern for a reason: a mining site already has the land, the substation capacity, and the local permits a data center needs, which is a faster and cheaper starting point than raw ground. For a county trying to steer new projects toward sites that already have industrial infrastructure, a former mine is close to the ideal candidate, which is likely part of why Spartanburg's moratorium carved out an exception for exactly that kind of site rather than banning conversions outright.
The rule written for the last fight
What made that reversal possible is a moratorium the council didn't have in February. On September 21st, council voted 5-1 for a one-year freeze on new data center applications, with the lone no vote coming from Jessica Coker, who argued no one had shown real evidence of a threat to residents. The ordinance, amended again on October 19th, caps new data centers at 65 megawatts, restricts them to existing industrial park sites, and bars on-site self-generation except for emergency backup power. It also carves out one specific exception: a former industrial or mining site at or under 65 megawatts can still move forward. That's the exact description of AIB's Tyger River site, and it's why AIB CLT1 and Jones Road Associates could clear council this month despite a freeze still technically in effect.
Spartanburg isn't moving alone. Neighboring Laurens County approved its own data center moratorium this year too, part of a wave of South Carolina counties writing siting, power, and self-generation rules before the next big project shows up rather than after one is already under construction. Spartanburg's version, with its specific carve-out for former industrial and mining sites, is among the more detailed of them, built directly out of what the county had already lived through.
The self-generation ban wasn't written in the abstract. Spartanburg County's most expensive data center fight to date is Valara, the $2.8 billion campus on South Pine Street we covered here in October: an 11-turbine, up to 457-megawatt gas plant built to power the site directly, structured specifically so it would fall outside South Carolina's Utility Facility Siting Act review. The plant clears that law's 75-megawatt threshold several times over and still never went before the one board that reviews power plants, because it doesn't sell power onto the public grid. A county council that watched that play out in public, and watched a judge toss the neighbors' zoning lawsuit on procedural grounds without ever reaching the merits, had every reason to write a rule against doing it again.
That lawsuit is still alive, just not in front of that judge. The Southern Environmental Law Center said in October it would appeal the dismissal, and as of this month no appellate ruling has come down. A second Valara permit application, covering four more buildings, a power yard, and added cooling systems, is also still pending before the county, separate from the development agreement at issue here. None of that has slowed construction on the existing phase, which has continued without interruption through every stage of the legal fight.
Protected from the rule aimed at it
Here's the part that should give any county drafting a similar ordinance pause. The same November 16th meeting that advanced three new, 65-megawatt-or-under projects also finalized a separate development agreement locking in Valara's own development rights for ten years, shielding its 457-megawatt campus from whatever regulations, moratoriums, or zoning changes the county adopts in that window. Councilman Monier Abusaft voted no, as he had on the agreement's second reading, but it passed. The self-generation ban exists because of Valara. Valara is now the one project in the county with a signed contract saying that ban, and anything like it, doesn't reach it for a decade.
This is the same structural gap we flagged in Loudoun County, Virginia's by-right grandfather clause fight, just running through a development agreement instead of a vested zoning right. A moratorium only binds what hasn't already been locked in. For anyone doing diligence on a site in a county that just passed, or is about to pass, a data center moratorium, the question that actually matters isn't what the ordinance says today. It's whether the specific parcel already has a signed development agreement, annexation deal, or vested zoning right that predates it. That document, not the county's current policy, is what a buyer or a tenant is actually relying on.
The residents watching the math
Not everyone in the room read this month's votes as a win. Eric Allison, who founded the Facebook group No Data Centers in Spartanburg, called council members "cowards" after Monday's vote, said they should be ashamed, and told them every member needed to step down that day. His complaint wasn't only about the deals themselves: council pushed through 20 public hearings and 22 second- and third-reading votes in a single meeting, and Allison argued that pace is itself proof the county isn't actually listening to the people who keep showing up to object.
I think the honest read of this month in Spartanburg County is that the system is doing exactly what it's designed to do, just not all at once. A county that got burned by a self-generation loophole wrote a rule closing it, built the criteria specific enough that a bitcoin-mine conversion under 65 megawatts can still clear council in one meeting, and left open the harder question of what to do about the project that exposed the gap in the first place. Closing a loophole for the next developer and undoing what the last one already signed are two different jobs, and Spartanburg just did the first one. The second one is still sitting in a ten-year contract with Valara's name on it.