What a Kill Test report actually looks like.
Real structure, real rigor, illustrative numbers — not a specific client's deal.
1. Executive Decision
Go/No-Go: Pause Pending Confirmation
Rationale: The site's zoning and land-control position are favorable and the utility's own territory map places it within a serving footprint with existing nearby infrastructure. Two genuine open questions keep this from advancing further: the specific substation adjacency claimed in county records has not been independently confirmed against an outside dataset, and the project has no documented water pathway yet for the stated cooling approach. Both are concretely resolvable — neither is a fatal condition today.
4. Domain Dashboard
| Domain | Risk | Key driver | F / R |
|---|---|---|---|
| Power | Claimed substation adjacency not independently confirmed against HIFLD | 2 / 1 | |
| Zoning / Entitlement | By-right use outside incorporated city limits; no rezone required | 2 / 0 | |
| Water / Wastewater | No documented water pathway for the stated cooling technology yet | 1 / 1 | |
| Environmental / Physical | Outside mapped flood, wetland, and critical-habitat layers | 3 / 0 | |
| Commercial Readiness | Site control under option, not yet closed | 1 / 1 | |
| Community / Political | No active local moratorium or known opposition within 25 miles | 1 / 0 |
Appendix A — Evidence Ledger (excerpt)
Parcel sits within the serving utility's filed territory map.
County legal description references a nearby substation by name.
Parcel is outside the FEMA-mapped 100- and 500-year floodplain.
What the full report includes
The executive memo and domain dashboard above, full findings and a risk register for all six domains, required next actions with named owners, and seven appendices: the full evidence ledger, utility correspondence inventory, documents on file with hash-based chain of custody, nearby power infrastructure and interconnection-queue timing context, water-usage considerations, land-use and environmental constraints across six live nationwide GIS layers, and regulatory/market leads — every one of them this exact level of specific, never a paragraph that just restates the recommendation in different words.