A Texas Bitcoin Mine Fought the County Over Water and Noise for Years. Its Direct Line to the Grid Just Won It a $28 Billion Anthropic Lease.
Navarro County spent years fighting Riot Platforms over a noisy, thirsty Bitcoin mine. Anthropic just signed a 15-year, $28 billion lease for the whole site, built on a transmission line that skips Texas's interconnection backlog entirely.
Kerry Brewer didn't think much of the bitcoin mine going up in his county. "If you want to know my personal opinion about it, I don't think it's a good investment," the Navarro County commissioner told a reporter, after Riot Platforms' cooling fans and the water the company was pulling from a drought-prone part of Texas had already turned into a running local argument. That spring, Brewer voted against the company's request for a tax abatement on its next expansion. Six months later, he reversed himself and voted yes on a smaller version of the same deal. The mine that split a three-person commission is now the anchor of the biggest lease Riot Platforms has ever signed.
The tenant Riot wouldn't name until a filing did it for them
On November 4th, alongside its third-quarter earnings, Riot disclosed a 15-year, triple-net, powered land lease covering its entire Corsicana, Texas campus: 910 megawatts of critical IT capacity on a contiguous parcel the company has spent three years converting from bitcoin mining into AI infrastructure. Total contract value runs to roughly $28 billion, with average annual rent near $1.8 billion. Riot's own statement called the agreement the largest lease in company history and named the counterparty only as a "leading Frontier AI Lab." The company's 10-Q, filed with the SEC the same week, didn't play along: it names the tenant as Anthropic. Combined with a smaller, 191-megawatt Rockdale lease the two companies signed in August, Riot now has 1,151 megawatts under contract and close to $38 billion in future data center revenue, built entirely on infrastructure that was mining bitcoin as recently as last year.
Riot is not the first bitcoin miner to make this pivot, and Anthropic is not the only AI lab making the bet. This blog has already covered TeraWulf's $19 billion lease with Anthropic on a dead Kentucky aluminum smelter site, with Google backstopping the credit. What makes Corsicana a different case, not a repeat of that one, is what the site already had before any AI company showed up: a working high-voltage interconnection, tested for years against a load that could cut itself off on command. A smelter site and a bitcoin mine both offer cheap land and existing power infrastructure. Only one of the two comes with a grid connection built to behave exactly like the thing a data center's utility most wants from it.
The wire that was already there
What makes Corsicana worth more than another patch of Texas scrubland is a detail that has nothing to do with Anthropic and everything to do with timing. ERCOT's interconnection queue has backed up badly enough that the state now makes large loads post cash deposits just to get their requests studied before anyone commits to building anything, the subject of the interconnection deposit rule this blog covered last month. Corsicana doesn't have that problem. The site carries a direct 345-kilovolt transmission connection, built years ago to run a bitcoin mine that could cut its own load to near zero whenever the grid needed the relief. Analysts tracking Riot's disclosures have said that existing connection sits outside the batch interconnection review that newer, larger projects now have to clear. A deal this size usually waits years on a queue position. This one didn't have to, because the hardest problem in Texas power right now was already solved on this parcel, for a reason that had nothing to do with artificial intelligence.
Abbott's standards, tested on a live deal
Texas Governor Greg Abbott ordered the Public Utility Commission and ERCOT in August to pause approvals for new data center grid connections until regulators could audit water use, power demand, and tax incentives project by project. Two weeks later, his office announced that Riot Platforms had committed to comply: the company would cover its own grid-upgrade costs, reuse water rather than draw fresh supply where it can, and forgo taxpayer-funded incentives. That is the right instinct, the same one this blog has tracked favorably in utility contracts from Michigan to Wyoming: make the company that needs the power absorb the cost, rather than spread it to everyone else's bill. It is also, so far, a commitment stated in a press release. Whether it holds up against the county's own tax records is the next thing worth checking, not something the announcement itself settles.
The fight that paid for the diligence
Corsicana residents have been arguing about this site since 2022, when a group calling itself "We Do Not Want This" protested the original bitcoin mine's noise. The tax fight came later and ran in two acts. In March 2024, Navarro County commissioners declined a reinvestment zone that would have saved Riot nearly $14 million in property taxes over a decade, tied to a company promise of 180 full-time jobs. That October, on a 3-2 vote, with Brewer reversing his earlier opposition, commissioners approved a smaller abatement instead: a $380 million minimum taxable value and a floor of 140 full-time jobs by January 1, 2026. Riot has cited different job figures at different points, including 270 projected at its original 2023 groundbreaking and 150 full-time employees plus 200 contractors on its own company materials. None of those numbers has ever been large next to 910 megawatts, and critics have made exactly that point: a campus this size supports a workforce you could fit in a high school cafeteria.
Water and noise were never fully resolved either, just managed. Riot pays roughly $2.1 million a year to reserve lake water for cooling, on top of a city water allocation that can run up to 1.5 million gallons a day, and the company has told commissioners it is drilling wells into the Woodbine Aquifer and storing rainwater in an 18.5-acre retention pond to cut its draw from both. Riot said years ago it would use immersion cooling to quiet the site down; whether that technology, still considered experimental for a campus this size, actually got installed is not something I could confirm in the most recent reporting available. Early on, activists said county officials turned down their request for a town hall to address the noise and water concerns directly. A deal this size usually gets a public forum. This one, for years, didn't.
I think the real story here is which kind of diligence gets done first. The engineering question, whether this site can actually take a gigawatt of load without waiting behind every other Texas project in ERCOT's queue, got answered years ago, as a side effect of building a bitcoin mine nobody expected to turn into Anthropic's biggest lease. The public-interest questions, whether 140 jobs is a fair trade for a $380 million tax break, whether an aquifer built to supply a farming county can take this draw indefinitely, whether a company's water and noise promises get checked against what actually gets built, are still open, just with a bigger number and a new counterparty attached. Anthropic inherited a wire that already works. It did not inherit answers to the questions Navarro County has been asking since before anyone outside Texas had heard of Corsicana.