Entergy Wants Dustin McAnn's Pasture for Meta's Power Lines. He's Suing the Regulators Who Made That Easier.
A Louisiana rancher found survey stakes in his pasture in August. By November his coalition was suing state regulators over the fast-track rule Entergy is using to build Meta's gas plants -- and take his land to power them.
Dustin McAnn didn't get a hearing notice. He got survey stakes, pounded into the pasture behind his house in Lincoln Parish, Louisiana, sometime in early August. He asked around and found out what they marked: a roughly 58-mile, 500-kilovolt transmission line Entergy wants to build across his land and his neighbors', running toward a connection in Webster Parish as part of the power build behind Meta's Hyperion data center campus, almost 80 miles away in Richland Parish. Nobody at Entergy or the state asked him first.
A barn meeting, then a lawsuit
McAnn didn't wait for a hearing to organize. Within weeks he'd founded the Louisiana Landowners Coalition, and by late August ten landowners who'd gotten the same survey stakes or the same letters were meeting in his barn. On October 14th, Entergy filed an expropriation suit -- Louisiana's name for eminent domain -- in Lincoln Parish's 3rd Judicial District Court, seeking rights across 14 tracts whose owners hadn't agreed to sell. The company says it sent independent appraisals and offered more than assessed value before suing, and that the line serves a real public purpose: meeting demand growth and improving grid reliability in north Louisiana, Meta's campus included.
Alliance for Affordable Energy executive director Logan Burke says that kind of argument tends to win. A state commission's finding that a project serves the public necessity "carries an enormous amount of weight" once a case reaches a courtroom, she says -- judges rarely second-guess one. That's exactly why the fight over how the commission reaches that finding, not just the fight over Entergy's price, is the one landowners are picking first.
The directive the land fight runs through
The land case and the regulatory case are connected by one piece of paper. At a December 17th, 2025 meeting, the Louisiana Public Service Commission adopted a directive at Commissioner Jean-Paul Coussan's request, echoing Governor Jeff Landry's "Louisiana Lightning Speed" executive order on permitting -- letting a utility skip procedural steps that would otherwise slow a large project's review. Entergy intends to use it again in December, when it asks the commission to approve seven more gas plants and additional transmission for Meta's campus. Cleco Power is already using the same directive for a different company's project, Applied Digital's proposed Delta Forge 1 campus in Rapides Parish -- proof this isn't just an Entergy-and-Meta story.
On November 9th, McAnn's coalition, along with the Louisiana Citizen Advocacy Group and Save My Louisiana, sued the commission in Baton Rouge. Their attorney, William Most, argues the only public notice the commission gave before adopting the directive was a single agenda line: "Directive on Commission's Lightning Initiative. At the request of Commissioner Coussan." That, he says, doesn't meet the Louisiana Constitution's bar for changing how the commission operates. The suit leans on a 1977 Louisiana Supreme Court case, asks a judge to declare the directive void, and seeks an injunction delaying any commission action taken under it.
The Louisiana Constitution requires the Public Service Commission to be transparent with the public when it tries to change its rules. It didn't do that here.William Most, attorney for the plaintiffs
The commission disagrees. Executive counsel Kathryn Bowman has called the directive "not a rule change," and says the underlying standard hasn't moved: a utility still has to prove its project serves the public interest at the lowest reasonable cost. That's true as far as it goes. It's also exactly why landowners are fighting the process now, before the December vote, instead of waiting to fight Entergy over the bill afterward -- a finding that a project serves the public interest doesn't just approve a power plant. By Burke's account, it's the same finding a court leans on when a utility goes to take someone's land for it.
A number Entergy didn't volunteer
Two weeks before that December vote, Entergy gave regulators a preview of what "lowest reasonable cost" can mean in practice. A quarterly filing reported by WWNO on November 19th shows the Waterford 5 gas plant built for Meta's campus now costs $1.755 billion -- $676 million, or 63%, more than the $1.079 billion Entergy originally estimated. The filing's expenditure breakdown is redacted, so the public record doesn't say what drove the overrun. Burke says it was "clear from the beginning" that Waterford 5 would cost more than Entergy said it would.
I'd call a 63% jump in a redacted filing exactly the kind of number this blog's own Kill Test exists to catch: a figure that moved substantially after the fact, with the receipts blacked out, delivered to the same commission that's being asked, under a directive its own staff concede skipped public notice, to approve seven more plants built the same way.
What the air near the campus is already showing
Four days later, on November 23rd, WWNO reported preliminary results from a community air-monitoring effort near Holly Ridge, inside Richland Parish where the Hyperion campus sits. An analyst reviewing a resident's own monitor found that roughly two-thirds of hourly fine-particulate readings came in at or above the EPA's annual health benchmark of 9 micrograms per cubic meter, with the single highest reading spiking to 252. That comparison carries a real caveat -- the EPA figure is an annual average, not an hourly limit, so this isn't a direct legal exceedance -- and the nearest official state monitor sits more than 30 miles away, at the Monroe airport. It's preliminary data, not a permit violation. It's also the only close measurement anyone has. Residents have described construction dust at the site as "like a sandstorm." The Sierra Club has separately argued that Meta's own air permit should classify the site as a major pollution source rather than a minor one -- a dispute over turbines Entergy is building and permitting separately from Meta's own facility.
None of this erases the other side of the ledger. This blog has already covered the real schools-and-roads money Meta is putting into Richland Parish, and the tax revenue the parish is already banking because of this campus. Entergy's underlying case for more north Louisiana transmission capacity isn't invented, either; that grid genuinely needs it, campus or no campus. But three separate pieces of the same project surfaced in the same two weeks: a transmission line Entergy is prepared to take by force from a man who found out from a surveyor's stake, a cost figure that moved 63% behind a redaction, and air data that complicates the company's own permit math. None of it went to a second vote. The commission is scheduled to decide on the seven new plants December 16th. If McAnn's lawsuit doesn't delay that date, Louisiana will find out within weeks which number -- the developer's, the regulator's, or the landowners' -- was the one worth believing.