Carbon County, Utah Approved Valar Atomics' Nuclear Data Center Campus. The Reactor Count Just Dropped From 456 to as Few as 40.
Carbon County cut Valar Atomics' reactor pitch from 456 to 40-120 and approved the permit anyway, without the public hearing residents expected on a project whose reactors the NRC still hasn't certified.
On Thursday night in Price, Utah, protesters carried signs into a Carbon County Planning Commission meeting that wasn't a public hearing, by design. One was escorted out before the vote. The commission approved the permit anyway, 4-1, clearing the way for Valar Atomics' Raceway Energy Campus: a 640-acre nuclear-and-gas-powered data center complex that, six weeks ago, was pitching itself as 456 reactors generating 9.6 gigawatts. The permit the commission just approved covers somewhere between 40 and 120.
We wrote about the earlier version of this project, then called Project Beehive, on October 2nd: a company founded in 2023 by 27-year-old Isaiah Taylor, which had raised more than $1.5 billion in well under a year, proposing to build something close to Utah's entire peak grid capacity on a stretch of coal country outside Price, using a reactor design the Nuclear Regulatory Commission had never licensed. Six weeks later, two things changed. The first is real progress: Carbon County's planning commission signed off on an actual, conditioned permit, not just a state land lease and a pending federal application. The second is that the headline number got a lot more credible. Forty to 120 reactors generating roughly 3 gigawatts is still an enormous bet for a county of about 20,000 people. It is not 456 reactors at 9.6 gigawatts, and the gap between those two numbers is most of what separates a pitch deck from a project a planning commission can actually vote on.
A plan that got smaller, and real
The permit, now branded the Raceway Energy Campus rather than Project Beehive, covers the same roughly 640 acres of state trust land near Wellington that the Utah Trust Lands Administration Board approved back in September. What changed is the shape of how Valar actually plans to build it. A natural gas plant goes in first, powering manufacturing, labs, and the data center buildings themselves until any reactor clears licensing, which means the campus doesn't have to wait on the Nuclear Regulatory Commission to start drawing revenue, and neither does the county's tax base.
That tax base is the whole reason this county keeps saying yes. Carbon County mined almost 10 million tons of coal in 2006 and hasn't mined a pound since 2023; the mines that once employed thousands are gone, and county officials have made clear for more than a year now that they see data centers, nuclear-powered or otherwise, as the industry that replaces them. Valar isn't even the only bet on the table. A second, unrelated complex nearby, nicknamed Jurassic Spark, would run purely on a conventional gas plant rather than reactors at all. A county this short on alternatives doesn't have the luxury of being choosy about which version of the same wager it accepts, and Thursday's vote reads less like enthusiasm for nuclear power specifically than like a county that decided it couldn't afford to say no to either project twice.
The planning commission attached 26 conditions to the approval, covering noise limits, security, and an emergency response plan Valar has to develop jointly with local agencies. One condition requires the company to use industrial water rather than culinary water, backed by a water management plan it still has to produce. Valar also can't pull a single building permit until it holds at least three public meetings in Carbon County, a real commitment, even if it comes after, not before, the permit that actually mattered.
Administrative, not a hearing
Here's the part drawing the sharpest local criticism, and it isn't the reactor count. Carbon County Attorney Christian Bryner told the planning commission upfront that Thursday's meeting wasn't a public hearing, because Utah law treats a conditional-use permit application like this one as an administrative decision rather than one requiring case-by-case comment. His position was that the county commission already took public input when it adopted the zoning rules that make this kind of project allowed on this land in the first place. Residents who had organized a petition asking the county commission for a temporary moratorium on large energy projects hadn't gotten an answer to that petition by the time the vote happened.
Commissioner Leo Hardy asked at the meeting why the moratorium petition had gone unacted on, and said afterward, in an email to residents, that an earlier exchange he'd had with Valar CEO Isaiah Taylor left him concerned the process had been handled with a thumb on the scale. The one dissenting vote, Commissioner Lisa Simmons, pressed Valar on how much heat its reactors would release into the surrounding desert during the hottest months of the year and got no specific number back. She voted no. Four of her colleagues voted yes anyway, over the signs and the protester led out of the room.
What's licensed, and what's still a plan
None of Thursday's news changes the piece of this project that actually determines whether it gets built. No reactor design Valar has proposed has been certified by the Nuclear Regulatory Commission, for this site or any other. And the Bureau of Land Management's review of the much larger federal parcel this campus would eventually need is still sitting at the same early-stage posture it was at in October: an application received, not yet confirmed complete, let alone approved. A county planning commission can approve a conditional-use permit on land the county actually controls. It cannot license a reactor, and it cannot make a federal land review move faster than the agency running it chooses to.
We've written before about the gap between a company's funding round and a working power plant. Thursday's vote narrows that gap by exactly one rung on the evidence ladder: a real, conditioned local permit instead of just a lease and a filing, which is genuine progress. It does nothing to the two rungs above it that actually decide whether reactors get built on this land at all, and a Kill Test run on this site today would still mark federal land control and reactor certification exactly where they were in October: not yet.
I think the real story out of Price this week isn't the reactor count, even though 40-to-120 is a far more honest number than 456 ever was. It's that the one decision Carbon County could actually make on its own, whether to approve this permit, got made without the one thing the people living next to it had asked for: a formal chance to be heard before the vote, not after it. The county attorney is probably right that the law didn't require one. That's a description of what happened, not a defense of it.