Tri-County Electric Cooperative (Texas), large load request framework

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusApproved  Last reviewed 2026-10-14
Applies atApplied to all large loads from 2 MW up
What the filing saysBoard-approved process (April 2026) rather than a filed rate. Four steps, each completed before the next: (1) electric service request with an NDA, (2) a reimbursable services agreement under which the developer funds engineering, legal and consulting studies up front and replenishes the funds, (3) a construction development agreement under which the developer pays all construction, equipment and infrastructure costs up front, and (4) a long-term electric service agreement that covers transmission and energy procurement cost risk. The cooperative states members should not subsidize large loads. Texas SB 6 separately applies to loads typically above 75 MW.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Tri-County Electric Cooperative 'Current Conversations' article on large load risk (tcectexas.com, read in full). Specific contract terms are not published.

Get an email when this changes

Other utilities in Texas

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.