Tampa Electric, proposed Large Load Customer Service (LLCS-1 and LLCS-2)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-10-14
Applies at50 MW or more anticipated monthly peak load at a single location
What the filing saysPENDING, NOT APPROVED. Docket 20260146-EI: Tampa Electric's petition of September 30, 2026 (read) proposes two schedules plus a Large Load Customer Contract (LLCC). LLCS-1 covers the first gigawatt of large-load demand and LLCS-2 covers demand above it. Both: initial term of not less than 20 years from the in-service date, including a load ramp period of up to 5 years; the customer pays a demand charge, incremental generation, transmission and fuel transport charges (and an incremental PPA charge if one is used) on contracted capacity; three years' advance notice to end service, otherwise termination charges set in the LLCC; security (cash, letter of credit, investment-grade guaranty or insurance product) set in the LLCC. FPL's separate approved schedules are in its own row. Approval is expected late 2026 or early 2027.

Stated terms

Contract termInitial term of not less than 20 years from the in-service date, including a ramp (as proposed)

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

Tampa Electric petition and tariff sheets, Docket 20260146-EI, filed September 30, 2026 (floridapsc.com, read); timing from local news (baynews9.com, Oct 1, 2026).