Free tool
Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Tampa Electric, proposed Large Load Customer Service (LLCS-1 and LLCS-2) | |
|---|---|
| Status | Pending |
| Applies at | 50 MW or more anticipated monthly peak load at a single location |
| Last reviewed | 2026-10-14 |
| Contract term | Initial term of not less than 20 years from the in-service date, including a ramp (as proposed) |
| Ramp | Up to 5 years, inside the term (as proposed) |
| Take-or-pay (minimum bill) | Not stated in the filings we read |
| Collateral | Security (cash, letter of credit, investment-grade guaranty or insurance product) set in the Large Load Customer Contract (as proposed) |
| Exit fee | Termination charges set in the Large Load Customer Contract; the amount is not stated (as proposed) |
| Notice to reduce or end | Three years' advance notice to end service (as proposed) |
| Time to power | Not stated in the filings we read |
| Source | Tampa Electric petition and tariff sheets, Docket 20260146-EI, filed September 30, 2026 (floridapsc.com, read); timing from local news (baynews9.com, Oct 1, 2026). |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site