Otter Tail Power (South Dakota)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-10-12
Applies at75 MW and above (proposed)
What the filing saysOtter Tail petitioned the South Dakota PUC on July 27, 2026 (docket EL26-021) for a new very-large-customer class and a data-center rate schedule. Approval pending. Not confirmed: final terms, and the status of the state's data-center bill (sources conflicted). No large-load tariff was found for Black Hills Energy or Xcel/NSP in South Dakota (NSP's Minnesota tariff was approved May 15, 2026 with a 15-year minimum term; its Wisconsin filing is a separate matter).

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

South Dakota PUC docket EL26-021 correspondence (puc.sd.gov); KELOLAND coverage of the Otter Tail petition.