Oklahoma Gas & Electric (OG&E)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-10-09
Applies atNew customers: 75 MW minimum demand. Existing customers: adding 75 MW incremental, or growing past 125 MW total.
What the filing saysDraft large-load tariff filed with the Oklahoma Corporation Commission on June 17, 2026, following a state law (signed by Gov. Stitt, May 13, 2026) directing utilities to establish such tariffs. OCC review expected to take approximately 6 months. Pending approval as of this research -- not yet adopted. Per OG&E's June 18, 2026 press release: a 15-year term with up to a 5-year ramp, large-load customers pay 100% of grid connection costs upfront, and the filing describes billing minimums, strong financial collateral requirements, and early termination and capacity reduction fees. The press release states no minimum-bill percentage, collateral amount or fee amounts, and no cause number.

Stated terms

Contract term15-year term (per OG&E's June 18, 2026 press release)

6 more stated terms (contract term, minimum bill, collateral, exit fee, notice and time to power, as the filings state them) are shown to signed-in visitors. Create a free account to see them, or sign in.

Source

OG&E press release, June 18, 2026 (oge.com, read); KGOU/KOSU coverage (kgou.org, kosu.org). Filing and cause number not read.