Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Oklahoma Gas & Electric (OG&E) | |
|---|---|
| Status | Pending |
| Applies at | New customers: 75 MW minimum demand. Existing customers: adding 75 MW incremental, or growing past 125 MW total. |
| Last reviewed | 2026-10-09 |
| Contract term | 15-year term (per OG&E's June 18, 2026 press release) |
| Ramp | Up to a 5-year ramp |
| Take-or-pay (minimum bill) | The filing describes billing minimums; the percentage is not stated in the press release |
| Collateral | The filing describes strong financial collateral requirements; the amount is not stated in the press release |
| Exit fee | The filing describes early termination and capacity reduction fees; the amounts are not stated in the press release |
| Notice to reduce or end | Not stated in the filings we read |
| Time to power | Not stated in the filings we read |
| Source | OG&E press release, June 18, 2026 (oge.com, read); KGOU/KOSU coverage (kgou.org, kosu.org). Filing and cause number not read. |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site