Mississippi Power and Entergy Mississippi (Mississippi), special contracts for data centers

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusLaw or process only  Last reviewed 2026-10-14
Applies atNo published threshold; contracts are negotiated (EEI refers to a Mississippi Power Rule 27)
What the filing saysLOWER CONFIDENCE. Mississippi has no published large-load tariff in the sources found. Contracts are negotiated, and a 2024 special-session law (SB 2001) narrowed the PSC's normal oversight of new generation for large projects. Mississippi Power's agreement with Compass Datacenters (500 MW, eight data centers over eight years) was approved by the PSC. Terms were not found. Consumer advocates say large-load contract terms have been withheld.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Site Selection coverage; Earthjustice report, May 2026; EEI list (Rule 27 reference not confirmed).

Get an email when this changes

Other utilities in Mississippi

Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.