Alabama Power (Alabama PSC), large data center contract review and special contracts

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusLaw or process only  Last reviewed 2026-10-14
Applies at150 MW or more expected peak demand for the state-law review process (Act 2026-610, effective October 1, 2026); 30 MW or more for a special contract under Rate BTAL (Docket U-5024)
What the filing saysNOT A PUBLISHED TARIFF: terms are set in individual contracts reviewed by the PSC. The Alabama PSC adopted its review procedure on about October 6, 2026 (generic Docket 33709): the Commission must vote within 90 days or the contract is deemed approved (the earlier proposal was 60 days); it must find the pricing recovers the incremental cost of serving the data center and benefits other customers; Alabama Power files a public version of each contract and gives staff and the Attorney General an unredacted copy. Parties note the rules set no minimum terms that every contract must include, and contract length, minimum bill and capacity were redacted in the contract filed so far. Smaller loads use Rate FCR or Rate BTAL special contracts. Ask Alabama Power for the contract form.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

Alabama Reflector, Oct 7, 2026 and ABC 33/40 coverage of the PSC vote; Energy Alabama reply comments in Docket 33709; EEI list, Sept 2026. The PSC order itself was not read.