Westlake Had No Legal Way to Stop This Data Center. Keller Sued Anyway and Got a Noise Meter Instead of a Veto.
Westlake's own zoning gave a 1.1-million-square-foot data center a legal right to be built. Keller sued its neighbor anyway, and the settlement buys decibel meters and monitoring, not a veto.
Westlake and Keller, Texas sit next to each other in Tarrant County, and until this fall they'd never had much reason to argue. Westlake is one of the smallest, wealthiest towns in the Dallas-Fort Worth area, built around corporate campuses and golf courses. Keller is a much bigger, solidly middle-class suburb next door. In August, the two governments ended up on opposite sides of a lawsuit over 87 acres of ranchland that neither one, it turned out, actually had the power to keep empty.
The land sits along U.S. Highway 377, inside a Planned Development District Westlake approved years before PowerHouse, a Virginia-based data center developer, ever asked to build on it. Under that zoning, a data center is a use allowed by right -- meaning once a site plan meets the district's own rules, the town has no legal basis to say no. Westlake's planning staff said as much to its own Planning & Zoning Commission on August 4th, after four hours of public testimony: "Given the site plan's compliance with the applicable approval criteria, there was no available basis on which the Commission could deny the site plan." The commission approved it that night, over strong objection, because approving it was the only outcome the law actually allowed.
That didn't mean the opposition got nothing. Commissioners attached real conditions: additional sound walls, more trees, and cooling equipment chosen to cut noise, plus a building line Westlake says sits 506 feet from the nearest home, more than three times the town's own 150-foot minimum. It wasn't enough to settle anyone's nerves. Kevin Myers, who lives in the Keller neighborhood closest to the site, put the distance in blunter terms: "a few hundred feet from our property lines." Another neighbor, Jesse Smith, wrote on Facebook that there's "a not-zero chance" the project affects the area's water supply or electricity rates. A few miles down the highway, a Buddhist nun named Meshi Sarah Hudson, whose monastery sits near the proposed site, raised a different worry: that the noise and the sheer physical presence of a data center campus would reach a place built for quiet reflection. "I think the biggest concern is that we really don't know what we're dealing with," she said, adding that her community was prepared to pursue religious-freedom protections under state and federal law if the project substantially burdened its practice.
A city with no veto sues anyway
Keller's residents didn't wait for construction to start. The Lakes at Marshall Ridge homeowners association and two residents sued in Tarrant County district court, and on August 17th, Judge Kimberly Fitzpatrick issued a temporary restraining order blocking Westlake from voting on or taking any action on the project's development agreement. Keller's own city government went further and authorized its own legal action against its neighbor -- one city suing another over a private developer's zoning approval, not just residents suing a city. Mayor Kim Greaves pushed back on the idea that Westlake ever had real discretion here, noting that the 15 homes closest to the site, in the Lakes at Marshall Ridge subdivision, were built years earlier without Westlake's input on zoning and without any buffer requirement written into the deal. The restraining order held through most of September before it expired, with the underlying case still unresolved.
What $1.876 million actually buys
On November 5th and 6th, Keller, Westlake, and the landowner, Circle T Owner LP, announced they'd settled -- a deal that didn't block a single square foot of construction but did put real, checkable numbers on the table. The developer committed $1.876 million total: $1.5 million into a noise-mitigation fund, $300,000 to Keller's fire department, and $76,000 toward the legal and expert costs Keller had already run up fighting the project. More specific than the dollar figures are the noise terms themselves: a cap of 56 decibels at residential property lines during the day and 49 overnight, verified by an independent noise study and monitored quarterly for three years after the facility opens -- an extension from the one-year schedule first floated. The settlement's fine print also matters: Keller's own payout was conditioned on dismissing its claims against Westlake with prejudice, meaning this is the deal, not a pause before round two.
Westlake's Town Council approved the development agreement unanimously on November 12th, clearing the last procedural step. Mayor Greaves thanked the developer directly: "I want to thank PowerHouse for being an outstanding partner throughout this process." Keller's mayor, Ross McMullin, framed his city's own role differently: "Keller's first responsibility has been, and will always be, to protect our residents." Both statements can be true at once, and the settlement is the proof -- a city with zero legal power to stop the project still extracted a specific, monitored, dollar-backed commitment instead of nothing.
A noise meter is not a veto, and that's the point
This is a pattern we keep running into on this blog, just approached from a different angle. We've written before about Loudoun County, Virginia's by-right grandfather clause and about how Aurora, Colorado's Trident project was functionally locked in before most of the city knew its name. Westlake runs the same mechanism in reverse: instead of a moratorium arriving too late to stop an already-entitled project, here the entitlement itself -- a Planned Development District written years before anyone objected -- never gave the town a legal lever to begin with. The Kill Test asks whether a site's zoning is actually vested on terms a court would enforce, not just whatever classification happened to be sitting on the parcel the day the application landed. On that question, Westlake's answer was settled before the first public hearing ever happened.
None of this resolves what residents were actually worried about going in. The settlement buys monitoring, not silence -- a data center that stays under 56 decibels during the day is still a data center running next to a subdivision and, depending on wind and topography, within earshot of a monastery that isn't a party to any of it. Hudson's community's stated willingness to pursue a religious-freedom claim if the project substantially burdens its practice is still just that, a stated willingness, untested in any filed suit as of this writing. Smith's worry about water and electricity costs isn't addressed by a noise fund at all. A monitoring regime is a real, checkable commitment -- more than most data center fights produce -- but it answers one question out of several.
I think the useful lesson here isn't about noise limits specifically. It's about where the actual leverage sat the whole time. Keller's residents and its own city government spent four months fighting a project neither could legally block, and they still walked away with an independent noise study, a three-year monitoring schedule, and nearly $1.9 million earmarked for specific uses -- because a lawsuit, even one built on a weak legal footing, is still worth something at the negotiating table. For anyone doing diligence on a by-right site anywhere else, that's the number worth remembering: not the decibel limit, but the fact that the fight itself, win or lose in court, is what put a dollar figure and a monitoring clause into a deal that didn't legally require either.