Spotsylvania County Approved Its Biggest Data Center Yet, 4 to 3. For a Decade, the Developer Gets Back 60 Cents of Every Tax Dollar It Owes.
Spotsylvania County, Virginia approved a 2.1-million-square-foot data center campus over fierce resident opposition -- then agreed to hand the developer back 60% of the new tax revenue it generates for a decade, then 20% for ten more years.
Arlene's house in Spotsylvania County, Virginia, sits across from a stretch of industrial-zoned land that has sat empty for decades. It won't stay empty much longer. On November 17th, the county's Board of Supervisors voted 4 to 3 to approve the Crossroads Technology Campus: seven data center buildings totaling roughly 2.1 million square feet, spread across part of a 550-acre site, with three electrical substations -- one of which will tower over her property. She was one of hundreds of residents who called in, emailed, or showed up to ask the board to vote no. It voted yes anyway.
A split board, and a process built for this
The vote split the board cleanly. Chair Lori Hayes, along with Tim McLaughlin, Drew Mullins, and Deborah Frazier, voted to approve the special use permit; David Goosman, Jacob Lane, and Chris Yakabouski voted against it. It wasn't a surprise ending. The county's Planning Commission had already recommended approval back in September, 4 to 2, and local reporting has called this the first real test of Spotsylvania's special-use-permit process for a data center at this scale -- a process the developer, RCK Digital Crossroads LLC, cleared on schedule despite the opposition.
The number everyone cites, and the ones nobody has reconciled
The project's physical scale isn't in dispute: seven buildings of roughly 100 megawatts each, built on land zoned industrial. The electrical scale is murkier. RCK Digital's own utility filing put the site's total electric load at up to 894 megawatts, a number the regional electric cooperative itself flagged as coming from the applicant and not independently verified. That's worth sitting with before treating it as a planning fact -- a developer's own estimate of its future power draw is a claim, not a measurement, and it's the same gap GridPermit's Kill Test is built to catch: what's filed by the applicant versus what a utility, a regulator, or an inspection has actually confirmed.
The money is just as unsettled. The developer has promised more than $30 million a year in county tax revenue once the campus is fully built. RCK Digital's attorney separately cited a $245 million total figure. A county-linked projection reported elsewhere put the number closer to $371 million. Those three figures describe the same project, and nobody on the record has explained why they don't match. I'd treat all three as marketing numbers until the county publishes one it's willing to stand behind.
The part residents are angriest about isn't the vote
It's the arithmetic behind it. Under the deal the board approved, Spotsylvania returns 60% of whatever tax revenue Crossroads actually generates back to the developer for the project's first ten years, then 20% for the ten years after that. Combine that with the county's tax rate on data center equipment -- $1.25 per $100 of assessed value, among the lowest in the region -- against Fairfax County's $4.57 for the same category, and the county isn't collecting anywhere close to full value on this project for two decades, even by its own promised numbers.
Oh, it is a very much a sweetheart deal.Staats, Spotsylvania County resident
Staats is reportedly exploring whether residents have any avenue to appeal the board's decision. At the same meeting, a resident named Ehmer told the Planning Commission that the industrial zoning designation the county is leaning on to justify this approval was written more than 60 years ago, for a different kind of industrial use entirely -- not seven 100-megawatt buildings and three substations. Longtime resident Brian Peyton said his concern wasn't this decade, but the next several.
What the county actually got in writing
Set against that, Spotsylvania didn't approve this with nothing attached. The board imposed 57 conditions on the project, including roughly 300-foot buffers around the site and a commitment to keep about 63% of the land as open space. More specific still: a reclaimed-water system already under construction will route roughly a million gallons a day of treated wastewater to the data centers, rather than drawing that volume from the region's fresh supply. That's a real, checkable commitment -- the kind of thing a diligence process can actually verify later, unlike a tax projection nobody's willing to own.
Chair Hayes called Crossroads the "gold standard" of data center proposals the county has seen. Supervisor Frazier, who voted with her, said afterward she was frustrated by how much residents disliked a decision the board had made in good faith. Both things can be true at once: a project can clear every procedural hurdle a county has and still leave the people living across the street feeling like the hurdles were set too low.
What happens to a vote like this next
Staats isn't the first Virginia resident to go looking for a court after a board of supervisors approves a data center over local objection. Virginia law generally routes that kind of challenge to the circuit court by writ of certiorari, not to a second vote or a higher administrative board -- the same basic path the Southern Environmental Law Center and neighboring residents used, and lost on procedural grounds, in Spartanburg County's parallel fight over the Valara data center this fall. A certiorari petition in Virginia asks a judge to review whether the board followed its own ordinance and process correctly, not to re-litigate whether the project is a good idea. That's a narrower door than most residents expect going in, and one more reason the specific conditions attached to this approval -- the buffers, the open-space share, the water-reuse commitment -- matter more than the vote tally itself. Those are the terms a future lawsuit, or a future county staff member, can actually hold someone to.
Zoom out and Spotsylvania isn't acting in isolation. One Fredericksburg-area outlet covering this vote asked plainly whether the county is becoming "Loudoun County data center alley" -- a reference to the Northern Virginia county that built the densest concentration of data centers on earth and is now the same jurisdiction this blog has covered narrowing its own by-right approval category in response. Spotsylvania and its neighbor Stafford County both had major data center hearings on their calendars the same week Crossroads came up for its final vote, and the region's comparatively low data-center-equipment tax rates -- the $1.25 figure cited above is shared across several of these counties -- are part of why developers are looking an hour south of Loudoun in the first place. A county that undercuts its neighbors on tax rate to win a project is making a deliberate trade, not an accident, and it's worth asking whether anyone on the board priced that trade against what Loudoun has already learned about living with it.
I don't think anyone in that room on November 17th -- not the four supervisors who voted yes, not RCK Digital, not Arlene -- actually knows yet whether this site draws 894 megawatts or something smaller, or whether the county nets $30 million, $245 million, or $371 million once the rebate clock runs out. Spotsylvania just became the first county in this region to find out what its own special-use-permit process does with a project this size. The next one deciding whether to run the same play should ask for a verified number before the vote, not a developer's own filing after it.