November 11, 2026 · Brendan Hogan, Founder, GridPermit

Dominion's Data-Center Pipeline Grew 13% in a Quarter. Virginia's Own Regulators Say That's Not Proof NextEra Should Own What Built It.

Dominion's data-center contracts hit 54.9 gigawatts this quarter. Days earlier, state staff said the $67 billion sale to NextEra hadn't proven ratepayers would stay protected, and the company's CEO wrote back that bigger 'demonstrably' is better.

On November 4th, in rebuttal testimony filed with Virginia's State Corporation Commission, Dominion Energy's chief executive made his case as plainly as a utility CEO ever does in a regulatory filing. "Bigger does not mean better in and of itself," Bob Blue wrote, defending his company's roughly $67 billion sale of itself, all of it, the utility that serves more than 2.7 million Virginia electric customers, to Florida-based NextEra Energy, "but here it demonstrably does." Sixteen days earlier, the SCC's own staff had filed testimony saying close to the opposite: that Dominion and NextEra had failed to prove the merger wouldn't put reliable electric service at reasonable rates at risk. Public hearings on the deal opened the next day, November 5th, with the full evidentiary trial still ahead.

One day before Blue's rebuttal, on November 3rd, Dominion gave investors a very different kind of update, and a much better one. In its third-quarter earnings report, the company said its data-center pipeline in Virginia had grown to 54.9 gigawatts of contracted and prospective load, up 6.3 gigawatts, 13%, since the end of December. Operating earnings came in at $1.28 a share, up from $1.06 a year earlier, a 20.8% jump, strong enough that Dominion now expects to land in the top half of its own full-year guidance. That isn't a press release. It's an earnings call backed by SEC filings, describing a century-old utility growing about as fast as a century-old utility can grow.

The number that actually tells you something

Not all 54.9 gigawatts means the same thing, and Dominion's own breakdown says so. 12.2 gigawatts sit under signed Electric Service Agreements, the stage where a customer has committed and the utility can build against that commitment. Another 9.8 gigawatts carry construction Letters of Authorization. The remaining 32.8 gigawatts, more than half the total, is what Dominion calls detailed engineering: real work, but earlier work, that hasn't converted to a signed agreement yet. That ladder, from engineering study to signed agreement to steel in the ground, is the same evidence hierarchy GridPermit's own Kill Test applies to every developer's megawatt claim, and it's worth something that Dominion's investor materials show their own version of it rather than quoting one headline number and letting readers assume all of it is equally locked in.

This is, by any fair reading, a genuine Virginia success story. Weather-normalized electric sales across Virginia and South Carolina grew 3.4% over the trailing twelve months, a growth rate the utility hasn't seen in a generation, and it's funding a roughly $65 billion five-year capital plan: new transmission, new substations, new generation, built against demand that is, for once, showing up with signed paper behind it instead of a developer's slide deck. Three months ago, Virginia's regulators forced Dominion to bill large data centers directly for a transmission line built mostly to serve them, cutting the typical household's share of that cost by two-thirds. The system has real levers for making sure growth like this gets paid for by the customers causing it. The open question this month isn't whether the growth is real. It's who gets to own the company managing it.

Why the state's own staff said no

NextEra agreed in May to buy Dominion outright, folding Dominion Energy Virginia into what would be the largest electric utility holding company in the country. The companies filed their joint petition with the SCC on July 15th, and state law gives the Commission a set window to rule unless it extends that clock. On October 19th, SCC staff filed testimony recommending the Commission deny the merger as proposed, writing that the companies had failed to prove the deal wouldn't jeopardize reliable service at reasonable rates. Staff didn't stop there. They said they'd drop their opposition if Dominion and NextEra accepted a specific list of conditions: an independent board of directors for Dominion Energy Virginia, restrictions on dividend payouts, a ten-year guarantee on current Virginia staffing levels, a bankruptcy-remote holding structure walling the regulated utility off from NextEra's other businesses, and a bar on NextEra's own transmission affiliate building future transmission projects inside Dominion's Virginia territory.

Gov. Abigail Spanberger went further still, intervening in the case to say the SCC should reject the deal outright unless the companies accept binding ratepayer protections: a six-year rate freeze, larger bill credits, and firm protections against customer disconnections, enforceable commitments a regulator can hold them to, not promised benefits that may or may not survive past closing. Her office has said plainly that she will not watch the case from the sidelines.

Dominion and NextEra didn't reject staff's list outright. In the same November 4th rebuttal, the companies accepted some of the proposed protections and rejected others, including the rate freeze and the full ring-fencing structure staff wanted, offering a conditional version instead: a separate protective entity that would only activate if NextEra's own credit rating actually slipped. Blue's rebuttal argued that Virginia's legal standard for approving a deal like this one is, in his words, a reasonable one rather than the high bar critics were describing, and both companies have said publicly that they agree, as a matter of principle, that data centers should pay their own fair share of what it costs to serve them. NextEra CEO John Ketchum has said his company is preparing its own formal rebuttal ahead of the case's evidentiary hearing, which opens November 17th.

What a pledge is worth before an order says so

Underneath the testimony, the companies have put one concrete ratepayer number on the table: roughly $1.78 billion in bill credits for Virginia customers over the merger's first two years. That's a real, specific figure, and meaningfully larger than nothing. It's also, as of this week, a number in a filing, not a number in an order. That gap is the same one this blog keeps finding in every pledge a company makes about a data center project, from a hyperscaler's voluntary community compact to a developer's unaudited jobs estimate, and it applies just as much to a utility merger as it does to a construction announcement. A commitment a regulator can enforce, with real exposure if it doesn't happen, sits in a different category than a commitment a company offers voluntarily and can revise later. Virginia's own SCC staff is, in effect, asking the companies to turn their $1.78 billion promise and their fair-share talking point into the first category, not leave it sitting in the second.

The SCC doesn't have to decide any of this quickly, and it probably shouldn't. The evidentiary hearing starting November 17th is where witnesses get cross-examined under oath, not just where testimony gets traded back and forth on paper. FERC still has to weigh in separately, along with regulators in North Carolina and South Carolina, where Dominion's smaller service territories sit without a hard deadline forcing anyone's hand. The companies are targeting a close sometime in the second half of 2027, which gives Virginia more than enough time to get the conditions right instead of fast. Dominion's growth numbers are the best argument NextEra has for why this deal makes sense: a utility actually building what the data-center boom needs, at a pace almost nobody else in the industry is matching. They're also the best reason to get the ownership question right before signing off. Fifty-four point nine gigawatts of new load is exactly the kind of growth that makes a parent company's financial health, and its incentive to put Virginia ratepayers ahead of its own balance sheet, matter more, not less.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report