November 19, 2026 · Brendan Hogan, Founder, GridPermit

Indiana Called It the Biggest Investment in State History. Amazon Just Sold Most of the Campus, Then Leased It Right Back.

Blackstone's new data-center REIT paid $5 billion for 75% of 13 AWS buildings in Indiana and Mississippi, then leased every one of them straight back to Amazon on terms Amazon.com itself guarantees.

Nine buildings sit on former farmland along State Road 2 outside New Carlisle, Indiana, inside the Indiana Enterprise Center. When Governor Eric Holcomb stood up in April 2024 to announce that Amazon Web Services would spend $11 billion building there, the state's own press release called it the largest capital investment announcement in Indiana's history. Two and a half years later, Amazon still runs every one of those nine buildings. It just doesn't fully own them anymore.

On November 16th, Blackstone Digital Infrastructure Trust -- a new, externally managed real estate investment trust that Blackstone launched specifically to buy data-center real estate -- announced its very first deal: a roughly 75% stake in two joint ventures holding thirteen AWS data center buildings, for about $5 billion. Nine of those buildings are the New Carlisle campus. The other four sit in Madison County, Mississippi, part of the $10 billion commitment Amazon made there in January 2024, which Governor Tate Reeves called, at the time, "the single, largest capital investment that has ever been made in the state of Mississippi -- by a lot". Together the two campuses carry 647 megawatts of IT power capacity, roughly enough to run a mid-sized city, and all thirteen buildings are already complete, energized, and occupied.

What a sale-leaseback actually buys you

The deal is a sale-leaseback, a structure familiar to anyone who follows corporate real estate but newer to AI infrastructure: Amazon sold the majority of the entity that owns the buildings, then signed a lease to keep operating inside them as if nothing changed. The thirteen buildings are what the industry calls powered shells -- completed, energized structures built to a specific customer's power and cooling specifications, sold once they're actually running rather than while they're still a hole in the ground. Under the terms reported by Bisnow and other outlets, Amazon Data Services keeps roughly a quarter of the equity in each venture and leases 100% of the space back on a triple-net basis, meaning Amazon, not Blackstone, pays the taxes, insurance, and maintenance on buildings it no longer majority-owns. The initial lease term runs twelve years, with renewal options that could stretch it to thirty-two. Blackstone paid an initial capitalization rate of 7.0%, real estate shorthand for how much annual rent that $5 billion purchase price is expected to generate.

Blackstone isn't paying cash for all of it. Roughly $1.9 billion comes from money the trust itself raised in its IPO; another $2.5 billion is new, non-recourse mortgage debt secured against the buildings themselves, meaning Blackstone's broader balance sheet isn't on the hook if either venture ever defaults. The deal is expected to close in the fourth quarter. For Blackstone Digital Infrastructure Trust, this is its first acquisition since launch, which makes it look less like a one-off transaction than a template the trust is almost certainly hoping to repeat on other hyperscaler campuses.

This fits a bigger pattern than one trust's first purchase. US utilities are already planning something like $1.4 trillion in grid spending over the next five years to keep pace with data center demand, by one industry estimate circulating this fall. That kind of number only works if someone keeps paying for the buildings on the other end of those new wires for decades, not quarters. A REIT built specifically to own stabilized, fully leased AI data center real estate, financed partly through public markets, is one more sign that the money behind this buildout is starting to look less like speculative venture capital and more like the long-duration infrastructure finance that funds toll roads and power plants.

The guarantee is the point

I think the detail most worth noticing here is one easy to skip past: Amazon.com, the parent company, guarantees the lease payments. That is a meaningfully different promise than most of what gets called a deal in this industry right now. This blog has covered AI infrastructure agreements built on a nonbinding letter of intent, on a term sheet still being negotiated, and on a backstop that only activates if a tenant defaults in the first place -- real commitments, in some cases, but each one a rung lower on the evidence ladder than a corporate guarantee from one of the most creditworthy companies in the world. Here, the rent is owed whether or not AI demand ever wavers, whether or not any particular AWS customer renews its own contracts, and whether or not Blackstone's REIT ever buys another building.

That's exactly the question I'd want answered in any commercial-readiness review of a data center counterparty: not who holds title to the dirt, but who is actually, contractually, on the hook if the tenant walks. A triple-net lease with a parent guarantee is about as strong an answer as this business produces. It says more about Amazon's confidence in its own long-term AI infrastructure build than any groundbreaking speech would.

Mississippi's four buildings tell the same story, smaller

The Madison County campus doesn't carry New Carlisle's size, but it carries the same local stakes. Mississippi's legislature called a special session in early 2024 just to approve the incentive package behind it -- $44 million from the state plus a $215 million state loan to the county -- on a project Reeves said was four times the size of the previous record holder, Steel Dynamics' $2.5 billion plant in Lowndes County. The original commitment was tied to at least 1,000 new jobs, and Amazon has since layered on another $12 billion across the state, including a separate project in neighboring Hinds County. None of that changes with this sale. The lease runs to Amazon regardless of who holds the equity above it, so the property tax base, the jobs tied to operating the buildings, and the county's own financial planning around this project are no more exposed to Blackstone's capital structure than they were to Amazon's.

That's worth sitting with, because the obvious objection to a sale-leaseback is that it looks like a company raising cash it needs. Airlines and retailers have used the structure that way for decades, often right before trouble. I don't think that reading holds up here. Amazon just spent two and a half years and tens of billions of dollars building these campuses; selling a majority stake the moment they're stabilized and fully leased, at a 7% cap rate, to help fund the next build, is closer to a company recycling capital on assets that already work than one raising cash to cover a gap. Amazon keeping a quarter of the equity and the entire operating lease, rather than exiting outright, points the same way.

What I'll be watching is whether Blackstone's trust does this again. A first deal is a test case; a second and third one, on different hyperscalers' campuses, is a market forming. If institutional capital keeps showing up for AI infrastructure on these terms -- fully built, fully leased, parent-guaranteed -- it's a genuine vote of confidence that this buildout has moved past speculation and into something closer to ordinary infrastructure finance. That's a better story for New Carlisle and Madison County than any single groundbreaking ceremony, because it says the money behind the jobs is now built to outlast the news cycle that announced them.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report